Mohmand Dam

Located on Swat River about 5 km upstream of Munda Head Works in Mohmand Tribal District, KP, this project has a proposed completion date of December 2025.The main objectives of the dam are to mitigate the risk of floods, irrigate agricultural land of 16,737 acres, hydropower generation and socio-economic uplift of people of the area.

Salient Features:

Type of DamConcrete Faced Rockfill
Height of Dam213 m (700 ft.)
Gross Storage1.239 MAF
Live Storage0.676 MAF
Power Generation800 MW
Annual Energy2,862 GWh
Cultivable Command Area (CCA)16,737 Acres (Left side 9,017 Acres, Right side 7,720 acres)