BALOCHISTAN EFFLUENT DISPOSAL INTO RBOD (RBOD-III)



Location
Nasirabad, Jaffarabad Districts of Balochistan and Jacobabad, Kambar-Shahdadkot Districts of Sindh Provinces. mkzp (1)
Scope of Work
To provide the direly needed effluent disposal facilities for existing and proposed drainage projects, the work would increase crop production of agricultural land wasted due to ponds of water, increase in cropping intensity and environment condition will improve over Gross Commanded Area (GCA) of 0.709 Million Acres.mkzp (1)
Executing AgencyWAPDA
ContractorsPrevious: M/s Khyber Grace (Private) Ltd Islamabad.M/s Muhammad Ayoub & Brothers (Private) Ltd. Latest: M/s Ramzan & Sons (Pvt.) Limited, KarachiM/s Hasas – Tameer Associates (J.V)M/s Tameer Associates-Hasas (JV)
ConsultantsPrevious: M/s National Development Consultants & EASE-PAK (J.V) Latest: M/s G3 Engineering Consultants (Pvt.) Ltd Lahore in association with BM Consulting Engineers.
Commencement Date July, 2004
Completion Date June, 2021
1stRevised updated PC-IRs. 10,804.540 Million (Approved by ECNEC on 26.07.2017)
PSDP Allocation for 2024-2025
  1. Completed Works:
i.Hairdin Carrier Drain Extension from Chukhi to Miro Khan Zero Point (MKZP).
ii.Construction of Irrigation Channel for reutilization of 400 cusec of Balochistan effluent.
iii.RBOD Extension from Miro Khan Zero Point (MKZP) to Hairdin Pump Station.
iv.Re-modelling of Shahdad Kot Main Drain.
v.Surface Drainage System of Usta Muhammad and Hadero Drainage Units.
vi.Balance works of RBOD Extension Drain from RD 161+000 to 284+000.
vii.Balance works of Hadero Branch Drainage System.
viii.Balance works of Usta Muhammad Drainage System. 
  1. Overall Physical Progress:              100%
  1. Present Status
  • O&M is the responsibility of respective Provincial Irrigation Departments Govt of Sindh & Blaochistan. The completed works pertaining to Balochistan Province have been handed over to Irrigation Department GoB for O&M by December, 2021. However, Irrigation Department GoS yet to assume responsibility of O&M of completed works in Sindh province.
  • PC-I for Restoration of Flood 2022 Damages comprising of RBOD-III Project with an amount of                    Rs. 8,332.342 Million has been submitted to Ministry of Water Resources Government of Pakistan for its approval from competent forum, which has uploaded on iPAS on 08.06.2023.
  • 2nd Revised PC-I comprising WAPDA Bridge Financing & Liabilities amounting to Rs. 11,065.426 Million has been submitted to MoWR for approval of competent forum.