Bara Dam Project

Bara Dam Project

Location
The proposed dam is located across Bara River at the confluence of Mastura River in Khyber Agency, FATA.
Salient Features
Dam Type Earth Core Rockfill Dam
Height of Dam 302 ft
Gross Storage Capacity 85,363 AFT
Live Storage Capacity 62,434 AFT
CCA 41,729 Acres
Power Generation 5.8 MW (38.1 GWh)
Execution by WAPDA
Commencement Date March, 2020 (Expected)
Completion Date  5 Years after Commencement
Financial Status Local (Rs. Million) FEC (Rs. Million) Total  (Rs. Million)
Original PC-I Cost 14,208.00 - 14208.00
1st Revised PC-I Cost 26,044.00 - 26,044.00
PSDP Allocation FY 2018-19 - - -
Upto Date Expenditure 35.173 - 35.173

Status:       

 Construction will be started after:

  •   Detailed Engineering Design 
  •   Availability of funds
  •   Improvement in security conditions of the area

Incharge of the Project:  

Shahid Mahmood
General Manager (Hydro) Planning,
WAPDA, Sunny View, Lahore
Contact No. 0092-42-99202717
Cell No. 0333-4654348

Read 21508 times