Dasu Hydropower Project
English Chinese (Simplified) Urdu

Dasu Hydropower Project

Location
7-km upstream of Dasu Town on Indus River, 74 km downstream of Diamer Bhasha Dam and 350 km from Islamabad.
Salient Features
  • Dam Height
242 m  
  • Dam Type
RCC Gravity Dam
  • Installed Capacity
4,320 MW (Stage-I: 2,160 MW)
  • Annual Energy
21,485 GWh                              
  • Objectives
To Generate Electricity

Execution by

WAPDA

Consultants

                                   

DHC JV, M/s Nippon Koei (Japan) Lead Firm

M/s Dolsar (Turkey) with local sub-consultants of M/s DMC,       M/s NDC & M/s PES

Contractors

M/s China Gezhouba Group Company (CGGC) for Main Works

Commencement Date (Stage-I) June 23, 2017
Completion Date (Stage-I) April, 2026
Financial Status (Rs. Million) Local Foreign Total
PC-I Stage-I Cost (Nov 2019) (due to revised Land Cost) 292,432.610 218,547.500

510,980.110

 

PSDP Allocation 2021-2022 53,364.00 3,150.000 56,514.00
 

Status:-

Contract Package Contractor / Name of Contract Progress / Status
MW-01 Construction of RCC Dam and Allied Hydraulic Structures. 10.13%
MW-02 Construction of Under Ground Powerhouse and Allied Hydraulic Structures. 6.56%
KKH-01 Relocation of KKH (25 km).         28.97%
RAR-01 Construction of Right Bank Access Road (12 km).         89.21%
TL-01 Construction of 132 kV transmission line from Dubair to Dasu. 82.96%
LBRV-11 Construction of Resettlement Sites 23.93%
LBRV-12 Construction of Resettlement Sites 15.18%
PCI-01R Project Colony & Infrastructure 34.03%
Dasu-RV Construction of Resettlement Sites and Shatial Museum 32.37%
EM-01 Electro-Mechanical Works <1%
RAR-02 Construction of Right Bank Access Road (42 km) <1%

STATUS OF CONTRACTS AWARDED/ NOT YET COMMENCED

KKH-02 Relocation of KKH (37 km).                           
  • Mobilization advance paid.
  • Commencement was delayed due to non-availability of land.
  • Requisite land is now available.
  • Commencement expected soon.
RBRV-11 Construction of Resettlement Sites
  • Mobilization advance paid.
  • Commencement delayed due to inaccessibility to Resettlement Sites.

STATUS OF LAND ACQUISITION

  • Original land required for Project                                     9,875 Acres
  • Revised land required for Project                                     5,051 Acres
  • Land Acquired/ In-Possession                                          4,215 Acres
Physical Progress             9.00%

 

Incharge of the Project
Mr. Anwar-ul-Haq
General Manager/Project Director Dasu HPP
Contact No. 0092-998-407007
 

In Pictures

Dasu Site View
Image Detail
Dasu
Image Detail
DASU
Image Detail
WAPDA: Committe...
Image Detail

 

 
Read 91934 times