|
REHABILITATION UP-GRADATION & MODERNIZATION |
||
| Location | River Kabul at about 30 Km in North West of Peshawar. | |
| Purpose | The Project was completed under Colombo Plan in two phases, financed by Canadian Govt. The 1st phase consisted of construction of Dam, Irrigation tunnels and installation of four power generating units, each of 40 MW capacity with 132KV transmission system and completed in 1960. Two additional generating units each of 41.48 MW Capacity were added in 1980-81 in the 2nd phase thus raising the total installed capacity to 242.96 MW (say 243 MW). | |
|
Rehabilitation (Phase-I)
|
In the late
Eighties, the Power generating capability of Warsak Power Station
reduced to 150 MW due to the following two major problems.
In order to resolve of the above problems, the Governments of Pakistan and Canada planned a Rehabilitation Project to meet with the following objectives.
|
|
| Project Features Approved PC-I Cost Actual Cost Incurred Commencement Date Completion Date Works Complted |
Rs. 1325 Million (1992) Rs. 1000 Million incl C$ 27.0 Million 31-12-1996 30-04-2006 |
|
| Replacement/repair of Turbine components, intake gate repair, Draft tube repair, Rehabilitation of butterfly valves, Generator mechanical works, new trash racks & TRCM, Embedding of sill plates in concrete of spillway gates, Repair of Crane-rail, Filling of roof cracks in power house roof, Floor anchoring and Generator floor cutting etc. | ||
|
Rehabilitation/ Up-gradation scheme (Phase-II) |
The works carried out under Rehabilitation Project (Phase-I) were envisages about 20 years ago. Since then many more problems have cropped up due to further aging of Electro-mechanical equipment and old civil works. Wapda has planned to carryout second phase of Rehabilitation with the objective to ensure that the six (6) generating units of Warsak Power Station, having spent life of 50 years (Units 1~4) and 30 years (Units 5~6) are made capable to operate efficiently & reliably at the total installed capacity of 243 MW for another 40~50. Following reasons have particularly necessitated taking up the proposed Project. | |
| Feasibility Study | As a first step it is intended to hire the services of Consultants for carrying out a Feasibility Study and preparation of Detail Design & Tender Documents and PC-I for Rehabilitation, Up-gradation and Modernization of Warsak. The basic objective is to determine the most viable options, technical as well as economical keeping in view of the aging effects of Electrical & Mechanical Equipment and Civil Structures and then prepare Detail Design & Tender documents and PC-I for implementation of the Project. | |
| Scope of Studies |
|
|
| Expected Benefits | The benefits will
be worked out in the Feasibility Study, however according to the
preliminary estimation following benefits are envisaged.
|
|
| Status |
The process of hiring of Consultants was started in October 2009. After completion of all codal formalities, Consultancy Agreement between WAPDA and M/S RSWI (Canada)-DCE (Pakistan) JV was signed on September 13, 2011. The said Agreement became effective Dec. 12, 2011. The first site visit of Warsak Hydroelectric Power Station by the Consultants for Detailed Condition Assessment of E&M Equipment and Civil Works has been completed (from Dec. 17 tp Dec. 22, 2011). The preparation of Feasibility Study is in Progress. A second site visit of Warsak by the Consultant is expected in Feb, 2012. |
|
| Completion Time | 12 Months from the date of effectiveness of the Agreement. | |
| Estimated Cost & Schedule | Accurate Cost/Schedule will be determined by the Consultants in Feasibility study by Sep, 2012 depending on the most viable option. Tentative cost of the Project including. Consultancy for Construction Supervision is US$ 305 Million Implementation of Project is expected to start and 2014 and completed. | |
| Updated as on 31-03-2012 | ||