|
INFORMATION REGARDING PROPOSED
1. Introduction
Tarbela Dam Project is the capstone of
the Indus Basin Plan envisaged as replacement of water previously fed by
eastern rivers. The project is the backstay of Pakistan’s economy and
facilitates supply of irrigation water and production of power for
industrial, agricultural and domestic uses. Civil works of Tarbela Dam
started in 1968 by the international contractors M/S TJV under design and
supervision of M/S TAMS, were completed by 1974.
Main Features / Components of the
Project The project consists of 9,000 feet
(2,743 meters) long, 470 feet (143 meters) high (above the river bed)
earth and rock-fill embankment across the entire width of the river with
two spillways cutting through the left bank and discharging into a side
valley. Main spillway has a discharge capacity of 650,000 cusecs (18,406
cumecs), and auxiliary spillway 8,50,000 cusecs (24,070 cumecs). Two
auxiliary embankment dams 2340 ft. (713 m) & 960 ft. (293 m) long
respectively close the low level ridges in the left bank valley. A group
of 4 tunnels, each about half a mile long through the right abutment rock,
have been constructed for irrigation releases and power generation.
Irrigation tunnel 5 situated on the left bank, for which NESPAK were the
Project Consultants, was put into operation in April 1976. The reservoir is 60 miles (97 km) long,
100 square miles (260 square kilometers) in area and had initial gross
storage capacity of 11.62 MAF (14.34 BCM) with a live storage capacity of
9.68 MAF (11.95 BCM). Due to 0.11 MAF per year silt carried by inflowing
water, the gross and live storage capacity of reservoir as per
Hydrographic Survey 2007 has reduced to 8.067 MAF and 6.841 MAF (9.955 BCM
& 8.442 BCM) respectively. The total catchments area above Tarbela is
spread over 65,500 square miles (169,600 sq. km), which largely brings in
snowmelt supplies in addition to some monsoon rains. Average annual inflow
at Tarbela is 64 MAF. The power station on the right bank near
the toe of main dam houses fourteen power units on Tunnels 1, 2 and 3. Ten
(10) units each with generating capacity of 175 MW were installed on
tunnel 1 and 2 by 1985. Four (4) units each with an installed generating
capacity of 432 MW on tunnel – 3 have been commissioned in June, 1994. The
total power potential of the project has thus been enhanced from
originally planned 2,100 MW to 3,478 MW. Statistical Sketch of Structures
2.
Project Location 3.
Project Objectives The purpose of this study is to analyze and evaluate the recommendations made by 5th Periodic Inspection of Tarbela Dam on Sediment Management of Tarbela Reservoir for maximizing its economic return and prolong the useful life of the dam. The recommendations inter-alia propose WAPDA to commission a study for sediment transport dynamics investigation in the Indus River downstream of Tarbela Dam to assist in decision making regarding the feasibility of sediment evacuation from Tarbela Reservoir and other reservoirs, either existing or planned. |