SABAKZAI DAM PROJECT
Location About 65 KM from Zhob District Balouchistan
Dam
    Type
    Length
    Height
 

    Earth & Rock fill 
    395 M
    34.75 M

Canal Capacity 33 Cusecs
Storage 32700 Acre Feet
Area To Benefit 7300 Acres
Power Nil
Cost 1960.823 Million
Status Feasibility complete. PC-I approved, Work Substantially Completed.
River Sawar Rud Tributary Zhob
TIME LINES
  Planned Expected
PC-II    
PC-I 31.03.2007 30.06.2009
APPROVAL    
  Rs. In Million Remarks
PC-II

 

Approved by ECNEC
PC-I

1960.823

CDWP ECNEC
    30.04.2009 03.09.2009
PERFORMANCE REPORTS AS ON 31.08.2010
  Behind ...... days On target Ahead ..... days
PC-II      
PC-I

Delayed 9 months

 

FINANCIAL STATUS PC-II                                                                                              (RS. In  Million)

Head of Account Expenditure upto 30.06.2010 Budget Allocation 2010-11 Expenditure in FY 2010-11 upto 31.08.2010 Total Expenditure upto 31.08.2010
Admn   No expenditure booked by this office
Overhead and Central Payments
Consultants  
Assets  
Works  
Total  
PC-I                                                                                                                                                                (RS. In Million)
Head of Account Expenditure upto 30.06.2010  (F) Budget Allocation 2010-11 Expenditure in FY 2010-11 upto 31.08.2010 Total Expenditure upto 31.08.2010
Admn 57.125 6.220 1.197 58.322
Overhead and Central Payments 73.431 5.632 0.939 74.370
Consultants 66.79 - - 66.790
Assets 9.7  - - 9.700
Works 1472.245 70.459 0.138 1472.383
Total: 1679.291 82.311 2.274 1681.565


Includes overhead and central payments proportionately

Sabakzai Dam Completed Handover to Government Balochistan.


Sabakzai Dam Project Latest Information