BALOCHISTAN EFFLUENT DISPOSAL INTO RBOD (RBOD-III)
Location

On the Right Bank of Indus River within Nasirabad, Jaffarabad District of Balochistan and Larkana, Jacobabad districts of Sindh.

 Dam
Project Incharge Mr. Abdul Rashid Bhutto, Project Director
Phone Direct: (071) 5633179 Fax: (071)5631969
Time Lines
Initial Date Schedule completion date Allocated budge
04-6-2004 Establishment of PD Office at Sukkur. 30.06.2006 (As PC-I)
Rescheduled date of completion 30.06.2009
Rs.100.00 Million (FY 2003-2004)
Rs.400.00 Million (FY 2004-2005)
Rs.500.00 Million (FY 2005-2006)
Rs.500.00 Million (FY 2006-2007)
Rs.800.00 Million (FY 2007-2008)
Rs.1200.00 Million (FY 2008-2009)
Approvals
Approving Authority
Govt. of Pakistan (Ministry of Water & Power)
PC-2   Cost
-   -
PC-1   Cost
    4485.20 Million
ECNEC   Cost
    4485.20 Million
Funding Agency
Government of Pakistan
Performance report as on 31.10.2008
Behind .........days On Target Ahead ........days
Present Status

1. Tenders for Hairdin Carrier drain Extension from Chuki to MKZP and 6 Km North of Chukhi opened on
    27.01.2005. Letter of Commencement issued to Contractor on 21.03.2005. The work is in progress.
2. Tenders for RBOD Extension from MKZP to Hairdin Pump Station opened on 29.08.2005. Letter of
    Commencement issued to Contractor on 20.02.2006. The construction work is in progress.
3. Tender Documents for Construction of Irrigation Channel upto Chitti River opened on 26.01.2006.
    The construction work is in progress.
4. Tender for Construction of Hadero Drainage Unit (Contract R-III (d/1) opened on 17th May, 2006.
    Letter of Acceptance issued to M/s Muhammad Ayub & Brothers. The Construction work is in
    progress.
5. Tenders for Construction of Usta Muhammad Drainage Unit (2nd Contract R-III (d/2) opened on
    16th August, 2006. The Construction work is in progress.
6. Tender for re-modeling of shahdad kot main drain contract No. R-III (b/1) has been opened on 11th 
    July 2008 and under process of Award.
7. Allocation for fiscal year 2008-2009 is  Rs.1200 Million. 

Key mile stone Plan Actual
1. Hairdin Carrier Drain Extension from Chukhi to MKZP and 6 km North of Chukhi. 25.03.2005 25.03.2005
2. RBOD Extension form MKZP to Hairdin Pump Station. 20.02.2006 20.02.2006
3. Construction of Irrigation Channel for reutilization of 400 Cusec of Balochistan effluent. 23.05.2006 23.05.2006
4.Hadero Drainage Unit. 04.12.2006 04.12.2006
5. Usta Muhammad Drainage Unit. 12.02.2006 12.02.2006
6. Remodeling of Shahdad Kot Main Drain 01.06.2008  
Key Issues    
Description

Reference

Resolved by

-

-  
Financial Status 2008-2009
  a b c d f g
Initial Budget Current Budget Actual Spend  date R/Cost to completed Var. Reason
Fixed            
Admn + Central Payment 46.000 46.000 3.00      
Over Heads & Interest 353.617 353.617 121.540      
Variable            
Consultants 15.00 15.00 2.66      
Assets     -      
Works 785.383 785.383 249.534      

Total

1200.000

1200.000

378.234(P)

     

Note Var=(c+d)-b

Other Comments
NIL