|
RIGHT BANK OUT FALL DRAINAGE PROJECT (STAGE-1) (RBOD-I) |
|
Location |
Project area lies within Shikarpur, Larkana Dadu
Districts of Sindh. |
|
Project
Incharge |
Mr.
Raiz Ahmed Mughal Project Director |
|
Phone
|
Direct:
(071) 5631316 Fax: (071) 5630417 |
|
Time
Line |
|
Initial
Date |
Scheduled Completion date |
Allocated Budget |
|
01.07.1994
Establishment of PD Office at Sukkur |
30.06.1998
(As per PC-I)
Re-scheduled date of completion is 31.12.2008 |
1900.000
MRs
(2007-2008) |
|
Approving Authority |
|
Govt.
of Pakistan (Ministry of Water & Power) |
|
PC-2 |
COST |
|
- |
- |
|
PC-1 |
COST |
|
Original
|
Rs.4395.00
Million |
|
ECNEC |
COST |
Original
(Approved on 30.11.2006)Rvised |
Rs.4395.00
Million
Rs.14707.143 Million |
|
Funding
Agency |
|
Government
of Pakistan |
|
Performance report as on 31.10.2008 |
|
Over all
status Physical Achievements 77.50% |
|
Performance report as on |
|
Behind
_______
days |
On Target |
Ahead
_________ days |
|
Present
Status |
|
1)
Contract for extension of RBOD upto MKZP is awarded to
M/s Khyber Grace (Pvt. Ltd.) at contract
price of Rs.609.547 M. applied for Extension of Time.
2) Remodeling of MNVD from RD 220 + 00 to RD 342
+ 00 awarded to M/s Khyber Grace Pvt. Ltd. at
contract price of Rs.525.0 M. Work in progress. Applied for
Extension of time.
3) Remodeling of MNVD From RD 110 + 00 to
RD 220 + 00 awarded to M/s S.H Haq Noor & Co. at
contract price of Rs. 315.283 Work is in progress. Applied
for Extension of time.
4) Remodeling of MNVD From RD 00 + 00 to RD 110
+ 00 awarded to M/s M Ayoub & Brothers, at
contract price of Rs. 367.569 M. E/ Work is in progress.
5) Widening of IL-2 & IL-3 for 3500 cusecs are re-opened
Work have been awarded to M/s Malik Riaz &
Co. (Pvt.) Ltd. Lahore at contract Price 72.59 M.Rs applied
for extension of time.
6) Balance work of IL-1 including its widening have been
awarded to M/s Abrar Malik & Co. at contract
price 155.81 MRs. Rehandling work in progress. Applied for
Extension of Time.
7) Remodeling of Shahdadkot drainage system. Pre-design
survey Complete. Tender documents /
detail design preparation.
8) Remodeling of Mirokhan drainage system. Pre-design
survey Complete. Tender documents / detail
design preparation .
9) Balance work of Ratodero Pumping Station. Work
awarded on 27.09.2005 to M/s MRCL at contract
price Rs.16.5 MRs. 99% work completed. Only testing and
commissioning of 11KV line is
remaining.
Applied for Extension of Time. . |
|
Key
mile stones |
|
Plan |
Actual |
1. RBOD
Extension to MKZP
2. Remodeling of MNVD from RD 220+ 00 to RD 342+
00
3. Remodeling of MNVD from RD 110+ 00 to RD 220+
00
4. Remodeling of MNVD from RD 00+ 00 to RD 110+
00
5. Widening of IL-2 & IL-3
6. Balance work of IL-1 including its widening |
28.02.2005
18.04.2005
20.06.2005
01.09.2005
23.11.2005
31.12.2005 |
31.05.2008*
17.11.2008
19.11.2008
30.11.2008
30.06.2008*
31.12.2008* |
|
Key
issues |
Reference |
Resolved By |
|
1. The
progress of all the ongoing works suffered badly due to
unprecedented torrential rainfall / heavy floods in the
project area during June-July 2007. The construction
activities of ongoing works remained suspended for about
04 to 06 Months. The completion period of the RBOD-I
Project is therefore needed to be extended for about 06
months i.e. upto 31.12.2008. |
|
- |
|
Rebate in
IDCs |
|
- |