· Consultancy
agreement for detailed Engineering Design and
Preparation of tender documents have been signed
between WAPDA (Hydro) Planning & Phandar Hydro
consultants JV on 22.10.2010.
.
CMTL, WAPDA has completed the seismic refraction
survey and other geo-technical investigation and has
also completed the lab analysis for trenches and
pits. Results/Report have been submitted to the
Consultants.
.
Comments on design memorandum offered by WAPDA Organizations have
been sent to Consultants for consideration
in the final design.
.
A draft cost estimate has been submitted by the
Consultants for review and comments.
Incharge
of the Project
Engr.
Hasnain Afzal
General Manager (Hydro) Planning
Wapda Sunny View, Lahore.
Contact No. 0092-42-99202717
Mobile No. 0092-0300-8411244
|