NEELUM JHELUM
HYDROPOWER PROJECT
|
|
Organization |
The Project is
running through Neelum Jhelum Hydro-Power Company WAPDA,
headed by a Board of Directors. The Chairman of the BOD
is Chairman Wapda. Members of Wapda Authority and three
General Managers are Members of the Board. Chief
Executive Officer, the representative of Board of
Directors, has his office at Lahore whereas Project
Director (Chief Engineer) has his office at Muzaffarabad
(AJ&K). |
|
Location |
Neelum Jhelum Hydroelectric Project is located in the
vicinity Muzaffarabad (AJ&K). It envisages the diversion
of Neelum river water through a tunnel out -falling into
Jhelum river. The intake Neelum Jhelum is at Nauseri 41
Km East of Muzaffarabad. The Powerhouse will be
constructed at Chatter Kalas, 22 Km South of
Muzaffarabad. After passing through the turbines the
water will be released into Jhelum River about 4 Km
South of Chatter Kalas. Neelum Jhelum Hydroelectric
Project has installed capacity of 969 MW. The Project
will produce 5.15 Billion units of electricity annually.
A concrete gravity dam 135 m long and 47 m high will be
constructed on Neelum River at Nauseri. The dam is
designed for over-topping. The dam will create a head
pond of 8 million cubic meters which will allow a
peaking reservoir of 2.08 million cubic meters to meet
daily peaking of power for more than 4 hours. A six gate
tunnel intake structure of 280 cumec capacity, will be
connected with three conventional flushing surface
basins installed at their end for taking sediment back
into river.
The
total length of head race tunnel is 28.5 Km. A 15.1 Km
stretch of the tunnel from the Nauseri be constructed as
a twin tunnel system each with x-section of 42 Sq.m. The
remaining head race tunnel down to the surge chamber
will be a single tunnel having x-section of 82 Sq.m The
tunnels are shotcrete lined with a concrete invert. The
tunnel crosses Jhelum River approximately 380 m below
its bed. The tunnel will be accessed by 7 Adits for
removal of excavated spoil.
The
Surge Chamber consist of 340 m high riser shaft and 820
m long surge tunnel, Four steel lined Penstock tunnels
150 m long and having 3.8 m internal diameter will also
be constructed. The under ground power Station will have
4 units with a total capacity of 969 MW. The Power
Station will be connected by with Rawat Grid station
through 500KV double circuit transmission line.
|
|
SALIENT FEATURES |
|
Overall Project Cost
|
Rs. 130 Billion.
(US$ 2.16 billion)
|
|
Installed Capacity
|
969 MW, Four Units @
242 MW each |
|
Dam, Type
|
Concrete Gravity |
|
Height /
Length |
47 / 135 Meters |
|
Annual Energy
|
5.150 Billion
electricity Units |
|
Average Head
|
420 Meters |
|
Design Discharge |
280 Cumecs |
|
Tunneling |
Two; each dia; 7.3
meter - 15 km, One; dia; 9.6 meter-17Km,(Total 47
KM) |
|
EIRR
|
26% |
|
Implementation
Period |
8 Years |
|
PROJECT BENEFITS
|
|
Reduction of
dependent on thermal power
Saving in foreign
exchange
Employment
opportunity during construction and operation
Improved standard of
living infrastructure
Social-economic
uplift of the area |
|
PROJECT IMPLEMENTATIONS
|
|
Construction |
|
Construction Contact
was awarded, on July 07, 2007, to M/s CGGC-CMEC
Consortium China for implementation of the project
at a cost of Rs. 90.90 Billions. Construction
Agreement was signed on December 19, 2007. Letter of
Commencement was issued on January 30, 2008. contractor
has mobilized at Site. Preparatory works and
construction of Contractor's camps at Nosadda & Chatter
Kalas are in progress. |
|
CONSULTANTS
|
|
Neelum Jhelum
Consultants (NJC), a Joint Venture Comprising of MWH
International Inc. USA, NORPLAN A.S., Norway, National
Engineer Services Pakistan (Pvt.) Limited, Associated
Consulting Engineers ACE (Pvt.) Limited, National
Development Consultants of Pakistan, have been selected
for Engineer Design and supervision (EDS) as Project
Consultants. consultancy Agreement was signed on May 15,
2008 Letter of Commencement was issued on May 16, 2008.
Services have been started since June 03, 2008.
The Project will be completed in 93 months. |
|
FINANCING
|
|
GOP has approved
financial arrangement for project, (a) Established
Neelum Jhelum Hydropower Company for project
implementation, (b) Imposition of surcharge @ 10 Pisa
per unit on power tariff for NJHEP fund providing for
50% fund requirement (c) Balance equity to be arranged
through loans, skuk bonds etc.
Revised PSDP (2007-2008) allocation of Rs.5700 Million. |
|
LAND
ACQUISITION |
|
Project envisages
acquisition of approx, 2400 kanals of private and State
land in the project Area in Muzaffarabad District.
So far WAPDA has transferred Rs.705 Million to Govt. of
AJ&K as provisional cost of the Notified Private and
state land.
WAPDA has taken possession of 80% land. remaining is
under progress. |
|
|