|
NEELUM
JHELUM HYDROPOWER PROJECT |
|
Organization |
The Project is
running through Neelum Jhelum Hydro-Power Company WAPDA,
headed by a Board of Directors. The Chairman of the BOD
is Chairman Wapda. Members of Wapda Authority and three
General Managers are Members of the Board. Chief
Executive Officer, the representative of Board of
Directors, has his office at Lahore whereas Project
Director (Chief Engineer) has his office at Muzaffarabad
(AJ&K). |
 |
|
Location |
Neelum Jhelum Hydroelectric Project is located in the
vicinity Muzaffarabad (AJ&K). It envisages the diversion
of Neelum river water through a tunnel out -falling into
Jhelum river. The intake Neelum Jhelum is at Nauseri 41
Km East of Muzaffarabad. The Powerhouse will be
constructed at Chatter Kalas, 22 Km South of
Muzaffarabad. After passing through the turbines the
water will be released into Jhelum River about 4 Km
South of Chatter Kalas. Neelum Jhelum Hydroelectric
Project has installed capacity of 969 MW. The Project
will produce 5.15 Billion units of electricity annually.
A concrete gravity dam 135 m long and 47 m high will be
constructed on Neelum River at Nauseri. The dam is
designed for over-topping. The dam will create a head
pond of 8 million cubic meters which will allow a
peaking reservoir of 2.8 million cubic meters to meet
daily peaking of power for more than 4 hours. A six gate
tunnel intake structure of 280 cumec capacity, will be
connected with three conventional flushing surface
basins installed at their end for taking sediment back
into river.
The
total length of head race tunnel is 28.5 Km. A 15.1 Km
stretch of the tunnel from the Nauseri be constructed as
a twin tunnel system each with x-section of 43 Sq.m. The
remaining head race tunnel down to the surge chamber
will be a single tunnel having x-section of 82 Sq.m The
tunnels are shotcrete lined with a concrete invert. The
tunnel crosses Jhelum River approximately 380 m below
its bed. The tunnel will be accessed by 7 Adits for
removal of excavated spoil.
The
Surge Chamber consist of 341 m high riser shaft and 820
m long surge tunnel, Four steel lined Penstock tunnels
154 m long and having 3.8 m internal diameter will also
be constructed. The under ground power Station will have
4 units with a total capacity of 969 MW. The Power
Station will be connected by with Rawat Grid station
through 500KV double circuit transmission line.
|
|
SALIENT FEATURES |
|
Overall Project Cost
|
Rs. 130
Billion
(US$ 2.16 billion)
|
|
Installed Capacity |
969 MW Four Units @
242 MW each |
|
Dam Type |
Concrete Gravity |
|
Height /
Length |
47 / 135 Meters |
|
Annual Energy
|
5.150 Billion
electricity Units |
|
Average Head |
420 Meters |
|
Design Discharge |
280 Cumecs |
|
Tunneling |
Two; each Xn Area 43 m2
One; Xn Area 82m2 |
|
EIRR
|
26% |
|
Implementation
Period |
8 Years |
|
|
The Neelum Jhelum
Hydroelectric Project is split into the following
three main geographic areas.
-
NAUSERI
AREA (ALSO KNOWN AS C1)
A 47m high mass concrete gravity intake dam and sedimentation
basins near to Nauseri on the Neelum River. The dam
has four large low-level gates designed to pass
floods up to the 1:100 year recurrence period and
also allow the reservoir to be drawn for sediment
flushing. The sedimentation basins are designed to
trap sediments that could erode the turbine blades
at the powerhouse. The intake works are designed to
divert up to 280m3/s in to the headrace
tunnels.
-
HEADRACE
TUNNEL
(ALSO
KNOWN AS C2)
The headrace tunnel is 28.5 km long and conveys
the water from the intake area at Nauseri to the
Powerhouse area near Chatter Kalas. The tunnel
crosses under high ground and also across the
Muzaffarabad fault zone. The first 15.1 km comprises
of twin tunnels, each of x-section area 43m2
and
the rest of the route, a single tunnel of x-section
area 82m2 has been proposed. The tunnel
will be excavated by drilling and blasting, with
shotcrete and rock bolts for general support and
full concrete lining at localized weaker zones. The
invert of whole tunnel is concrete lined. The tunnel
crosses below the Jhelum river at a depth of 380m.
-
CHATTER
KALAS AREA
(ALSO
KNOWN AS C3)
The headrace tunnel will feed four
vertical-shaft Francis turbines with an installed
capacity of 969 MW housed in an underground
powerhouse. The water is discharged back into the
Jhelum River near Zaminabad through a 3.5 km
tailrace tunnel. Associated facilities include a
transformer hall, surge shaft, access tunnels, a 500
KV switchyard and housing facilities for the
operations and maintenance personnel.
PROJECT IMPLEMENTATION
Construction
Construction Contact
was awarded, on July 07, 2007, to M/s CGGC-CMEC
Consortium China for implementation of the project
at a cost of Rs. 90.90 Billions including Rs. 46.499
Billions foreign component. Construction
Agreement was signed on December 19, 2007. Letter of
Commencement was issued on January 30, 2008. contractor
has mobilized at Site.
Preparatory
works including construction of Contractor's camps
aggregate crushing & batching plant site access roads
and site / test laboratory have been completed.
The main works of the project have started:
* For Main
Headrace Tunnel excavation shortcreting and rock
bolting (from Adit A-1) upto 396m completed.
* For Diversion Tunnel excavation shotcreting and rock bolting upto
408 meter completed.
* Adits A-1
has been completed since August 2009.
* For Adit A-2 Tunnel excavation shotcreting and
rock bolting
upto 14821m completed.
* For Adit A-3 Tunnel excavation shotcreting and
rock bolting
upto 1394m completed.
* For Adit A-4 Tunnel excavation shotcreting and
rock bolting
upto 1176m completed.
* For Adit A-5 Tunnel excavation shotcreting and rock bolting upto
701m completed.
* For Adit A-6 cable tunnel excavation shotcreting
and rock bolting upto 684m completed.
* For Adit A-7 Tunnel excavation shotcreting and
rock bolting upto 10 m completed.
* For access tunnel to serge tunnel excavation
shotcreting and rock bolting upto 353m completed.
* For access tunnel (from Adit A-5) to main headrace
tunnel excavation shotcreting and rock bolting upto
285m completed.
* For drainage gallery for penstocks excavation
shotcreting and rock bolting upto 181m completed.
* For probe tunnel excavation shotcreting and rock
bolting upto 136m completed.
* For Manifold from Adit A-6 near penstocks
excavation shotcreting and rock bolting upto 34 m
completed.
* Excavation of desander area remained in progress.
* Work on access road to portal Adit A-7 remained in
progress.
Overall physical
progress is 14.5 % upto the end of JUNE 2010.
|
|
CONSULTANTS ENGINEERING DESIGN AND CONSTRUCTION
SUPERVISION |
|
Neelum Jhelum
Consultants (NJC), a Joint Venture Comprising of MWH
International Inc. USA, NORPLAN A.S., Norway, National
Engineer Services Pakistan (Pvt.) Limited, Associated
Consulting Engineers ACE (Pvt.) Limited, National
Development Consultants of Pakistan, have been selected
for Engineer Design and Supervision (EDS) as Project
Consultants. Consultancy Agreement was signed on May 15,
2008 Letter of Commencement was issued on May 16, 2008.
Services have been started since June 03, 2008. |
|
FINANCING
|
|
GOP has approved
financial arrangement for project
(a) Established
Neelum Jhelum Hydropower Company for project
implementation
(b) Imposition of surcharge @ 10 Paisa
per unit on power tariff for providing 50% fund
requirement for NJHPC
(c) Balance equity to be arranged
through loans, skuk bonds etc.
Negotiations for foreign component are in progress with
IDB, Saudi Fund and Republic of China.
Revised PSDP (2009-2010) allocation of Rs.16000 Million.
Overall Financial Progress is 20 % upto the end of June
2010.
|
|
PROJECT BENEFITS
|
|
*
Reduction of
dependent on thermal power generation through reducing
the import of fossil thereby saving in foreign
exchange.
* Employment opportunities during construction and later
on operation of the Project
* Improved standard of living infrastructure
* Social-economic uplift of the area |
Updated
upto
30.06.2010
|
LOCATION
MAP |