MIRANI DAM PROJECT
Location The Dam is located on Dasht River, about 40 KM west of Turbat in Makran Division of Balochistan.
Dam
Type: Concrete Faced Rock Fill Dam
Length at Crest: 3080 ft.
Height 127 ft.
Canal Capacity   377 Cusecs
Storage   0.3 MAF
Area to Benefit 33200 Acres
Cost 5811 Million
Const: Period 5 Years
Status Construction Completed on EPC / Turnkey Basis.
River Dasht.
Funding Agency Govt: of Pakistan.
Executing Agency Pakistan Water & Power Development Authority.
MIRANI DAM PROJECT BRIEF
* Mirani Dam is constructed on Dasht river having two tributaries Ketch river and Nihing river
* Catchment area of Ketch river is 4604 sq. miles.
* Catchment area of Nihing river is 3360 sq. miles.
* Irrigation system of Dam consisting two main canals Right Bank Canal & Left Bank Canal the distribution of each system is given below:
Distribution of Canal System
Right Bank Canal Left Bank Canal
* Length of right bank canal is 66268 feet * Length of right bank canal is 62499 feet
* Command area of RBC is 20800 acres * Command area of LBC is 12400 acres
* Capacity of right bank canal is 236 cusecs * Capacity of Left bank canal is 141 cusecs
* No. of Distributaries on RBC are four (DR1, DR2, DR3, DR4) * No. of Distributaries on LBC are four (DL1, DL2, DL3, DL4)
* No. of Minors on DR1 are 3 and No of water courses are 19 * No. of Minors on DL1 are 5 and No of water courses are 27
* No. of Minors on DR2 are 5 and No of water courses are 56 * No. of Minors on DL2 are 4 and No of water courses are 17
* No. of Minors on DR3 are 4 and No of water courses are 24 * No. of Minors on DL3 are 2 and No of water courses are 12
* No. of Minors on DR4 are 2 and No of water courses are 19 * No. of Minors on DL4 are 3 and No of water courses are 18
* Length of DR1 is 4500 feet * Length of DL1 is 14984 feet
* Length of DR2 is 18000 feet * Length of DL2 is 15728 feet
* Length of DR3 is 17193 feet * Length of DL3 is 15714 feet
* Length of DR4 is 7382 feet * Length of DL4 is 13871 feet
 
Mirani Dam Project Brief