|
UP-GRADATION AND REFURBISHMENT OF |
||
| Location | Mangla Dam/Power station is located on River Jhelum at about 120 Km from Islamabad. | |
| Purpose | Mangla Dam is a multipurpose Project. Primarily designed for Irrigation. The other by products are Power Generation. Fish Culture. Tourism and Navigation. | |
| Construction | Mangla Power House was completed in four stages. The initial phase comprising of four units of 100 MW each was completed in 1967-69. The first extension of Unit No. 5&6 (2X100 MW) was completed in 1974 while second extension comprising Unit No. 7&8 (X100 MW) was completed in 1981. The project attained its maximum capacity of 1000 MW with the final extension of Unit No. 9&10 (X 100 MW) in 1993-94. | |
| Dam Raising | Mangla reservoir had initial gross capacity of 5.88 MAF, which reduced to 4.674 MAF (Year 2005 and was likely to reduce further with the passage of time due to sediment deposition. Keeping in view the capacity loss due to sedimentation and provision for raising in the original design and construction, Raising of Mangla Dam was started in 2004 and the Project was completed in 2009. The Dam height has been raised by 30 feet while maximum conservation level increased from 1202 feet to 1242 feet corresponding to additional water storage capacity of 2.88 MAF. There will be additional energy generation of 644 GWh due to availability of more water and rise in net head of machines. | |
| Up Gradation/ Refurbishment Scheme: | There are four age groups of
Mangla machines units 1~4 (40 years), units 5~6 (35 years), Units 7~8
(28 Years) & Units 9~10 (15 years). The first 6 Units with age of 30~40
year have outlived their useful lives due to which more resources and
time are required for maintenance of old equipment besides less
operational reliability. Some of the important aspects are: |
|
In view of above, WAPDA planned to carry out Up-gradation & Refurbishment of the old Generating Units and Allied Equipment to ensure their optimized, reliable and sustainable operation in the Post Raised Mangla Dam Scenario. |
||
| Feasibility Study | As a first step, Feasibility study has been started to assess the present operating conditions of existing Civil Structures & Plant Machinery and to determine the most viable option, technical as well as economical, for Up-gradation / Refurbishment of the existing Units of Mangla Power Station keeping in view the aging effects on Electrical & Mechanical Equipment and to effectively utilize the improved power potential after Dam Raising. | |
| Expected Benefits | There are
different options for Up-gradation of Mangla Power Station. According to
preliminary studies at the time of Dam Raising, following benefits were
envisages:
|
|
| Status of Feasibility Study | Consultants Consultancy Agreement Date of Commencement Studies Time/ Completion Time Revised completion time Consultancy Cost |
MWH (USA) -NESPAK
(Pakistan) JV 27th April, 2011 2nd May, 2011 06 Months 08 Months (Dec, 2012) Rs. 163.6 Million |
| Scope of Services |
|
|
| Progress |
|
|
| Estimate Cost & Schedule | The Construction Cost under this option is expected to be US$ 339.7 Million with the ten (10) years completion time. Implementation of Project is expected to start in 2013. | |
| Updated as on 31-03-2012 | ||