KHAN KHWAR
HYDROPOWER PROJECT |
|
Location
|
The Project is
located on Khan Khwar River, a tributary of Indus River near Besham
District Shangla in N.W.F.P. at a distance of 245 Km from Islamabad. |
|
Brief scope of the Project
|
|
Installed Capacity
|
72 MW |
|
Design Discharge |
35 m3/s |
|
Gross Head |
254 m |
|
Pressure Tunnel |
4.557 Km |
|
Energy per annum |
306 GWh |
|
Main Components
|
Reservoir Dam Headrace
Tunnel Powerhouse Tailrace Switchyard |
|
Approving Agency |
ECNEC |
|
Date of approval
|
02.09.2002 |
|
Approval cost of Project
|
|
Local |
Foreign |
Total |
|
2718.607 |
2644.098 |
5362.705 |
|
Date of Commencement |
|
Original (as per Contract) |
Revised |
|
June 2003 |
|
|
Date of Completion |
|
Original (as per Contract) |
Revised |
|
Oct 2007 |
Oct 2008 / Sep 2009 |
|
Progress |
|
|
A-FINANCIAL
|
Local |
Foreign |
Total |
|
(i) |
Expenditure upto
30.06.2008 |
2267.760 |
1389.277 |
3657.037 |
|
(ii) |
Budget allocation 2008-09 |
395.000 |
780.000 |
1175.000 |
|
(iii) |
Exp during current
Financial year (upto 30 Sept. 2008 ) |
90.399 |
88.657 |
179.056 |
|
(iv) |
Expenditure upto date (i+iii) |
2358.159 |
1477.934* |
3836.093 |
|
B-PHYSICAL (upto Sept. 2008) |
Planned (%) |
Actual (%) |
|
(i) |
Civil Works |
99 |
51 |
|
(ii) |
E&M Works |
100 |
80 |
|
* Expenditure
incurred against Foreign Component has been met out of Cash Foreign
Exchange. |
|
Reason for Delay
|
- Late issuance of
Construction Order (12 Jan. 2005) due to delay in completion of
access roads.
- Effects of
devastating earthquake of 8th Oct. 2005 in form of frequent slides
on roads & project sites resulting from after shocks.
- Scarcity of local
labour in the area after earthquake.
- Adverse climatic
conditions.
- Slow progress due
to poor management of Chinese Contractor.
- Evacuation of
Chinese from Project sites due to security reason on 07 Nov 2007.
Resumption of Works at Project sites by end Apr. 2008.
|