KACHHI CANAL PROJECT

Location

Districts Muzaffargarh, D.G. Khan & Rajanpur in Punjab and Districts Dera Bugti, Naseerabad, Bolan and Jhal Magsi in Balochistan.

Project Incharge Shams-Ud-Din  Abbasi, Chief Engineer/PD
Canal Length 500 KM (300 KM in Punjab and 200 KM in Balochistan) In Phase-I 400 KM.
Off take Point Taunsa Barrage at River Indus.
Canal Capacity 6000 Cusecs
Distributaries 1500 KM (Phase-I : 105 KM)
Area to benefit 7,13,0001 Acres (Phase-I, 102,000 Acres)
Approved PC-I Cost Rs.31,204 Million
Commencement 04.10.2002
Completion 31.12.2008 (Phase-I)
30.06.2009 (Phase-II)
30.06.2010 (Phase-III)
Project benefits Rs.5 Billion per year on completion of whole project.
TIME LINES
Initial Data Schedule Completion Allocation
04.10.2002 Original 30.06.2007
Revised 30.06.2010 (Phase-I)
Rs.300 Million (FY 2002-2003)
Rs.900 Million (FY 2003-2004)
Rs.1260 Million (FY 2004-2005)
Rs.2588.354 Million (FY 2005-2006)
Rs.6270 Million (FY 2006-2007)
Rs.7375 Million (FY 2007-2008)
Rs.8500 Million (FY 2008-2009)
APPROVALS
Appointing Authority
Government of Pakistan
PC-II Cost
Revised Rs.170 Million
Rs.199.356 Million
PC-I Cost
  Rs.31204 Million
ECNEC Cost
  Rs.31204 Million
Funding Agency
Government of Pakistan
PERFORMANCE REPORT AS ON  31.10.2008
Overall Status
Behind  548  days On Target ___________ days Ahead ____________ days
PRESENT STATUS
STATUS

PUNJAB PROVINCE
KC-1: (RD 20 to RD 40) 6 Km. Cost: Rs.22.829 Million
.
Work 100% completed on 30.06.2004.
. 86% payment (Rs.14.70 Million out of 16.93 Million) of land   
  compensation distributed to the Land owners.
KC-2: (RD 40 to RD 106) 20 Km. Cost: Rs.875.342 Million
.
Work 100% completed on 10.06.2008
.
93% payment (Rs.55.20 Million out of 59.165 Million) has been
  distributed to the land owners.
KC-3: (RD 0 to RD 20) 6 Km. Cost: Rs.3274 Million
. Work commenced by M/s DESCON Engineering Ltd. Lahore on
  22.08.2007 and progress upto 30.09.2008 is 86.64% against 86.48%.
. 95.88% payment (8.984 Million out of 9.370 Million) of land
  compensation has been distributed to the land owners.
KC-4: (RD 106 to RD 531) 129 Km. Cost: Rs.9737 Million
. Work commenced by M/s SMADB-Liley-Shah Rukh JV Karachi on
  13.07.2005 and progress upto 30.09.2008 is 50.50% against 92%.
. 93.15% payment (Rs.618.319 Million out of 663.789 Million) of land
  compensation distributed to the land owners.
KC-5: (RD 531 to RD 1005) 144 Km. Cost: Rs.12452 Million
. Work commenced by M/s Central China Power Group JV Lahore on
  09.09.2006 and progress upto 30.09.2008 is 47.25% against 81%.
. 1.43% payment (Rs. 1.000 Million out of 70.000 Million) of land compensation  
  distributed to the land owners.

BALOCHISTAN

KC-6A: (RD 1005 to RD 1166) 49 Km. Main Canal Cost: Rs.1822 Million
. Work commenced by M/s SMABD-Lilley-Shah Rukh JV on 28.03.2006
  and progress upto 30.09.2008 is 56%  against 100%.
. 85.43% payment (Rs.79.227 Million out of 92.737 Million) of land
  compensation distributed to the land owners.
KC-6B: (RD 1166 to RD 1322) 47 Km. Main Canal and Distribution Cost:
   Rs.6657 Million.
.
Work commenced by M/s Frontier Works Organization (FWO) on 08.11.2007
  and progress upto 30.09.2008 is 7% against 88%.
. Funds amounting to Rs. 144.181 million deposited with Executive District Officer 
  (Rev) Dera Bugti for payment of land compensation to the affectees.
KC-6C: (12 Distributaries) 72 Km. District Dera Bugti Cost: Rs.2766.956 Million.
.
Work commenced by M/s SMABD-ShahRukh JV Karachi on 30.08.2007. and
  progress upto 30.09.2008 is 14% against 65%.
. Funds amounting to Rs.62.099 million  deposited with Executive District
  Officer (Rev) Dera Bugti for payment of land compensation to the affetees.
KC-7: (RD 1332 to RD 1512) 58 Km. Main Canal and Distribution Cost:
   Rs.7350 Million.
. Alignment of Main Canal 100% completed in District, Naseerabad and Bolan.
KC-8: (RD 1512 to RD 1645) 41 Km. Main Canal and Distribution Cost:
   Rs.6969 Million.
. Alignment of Main Canal 100% completed in District Naseerabad,
  Bolan and Jhal Magsi.

Key Milestone Plan Actual
Contract KC-1
Earthwork Rd 20 to 40
06 Jan. 2003
30 Jun, 2004
06 Jan. 2003
30 Jun, 2004
Contract KC-2
Earthwork Lining RD 40 to 106 of Main Canal
15 Otc. 2003
17 May, 2005/
31 Dec. 2007
15 Nov 03
10 jun 08
Consultancy Agreement - 04 Dec. 2003
Contract KC-3
Head Regulator and allied structures and Earthwork RD 0 to RD 20+-
15 May, 2007
31 Dec, 2008
22 Aug. 2007
-
Contract KC-4
Earthwork, Lining and Structures RD 106 to 530+400
15 Aug. 2004
06 Jan, 2009
13 Jul, 2005
-
Contract KC-5
Earthwork, Lining and Structure RD 531 to 1005
15 May, 2006
31 Dec, 2008
09 Sep, 2006
-
Contract KC-6A
Earthwork and structures RD 1005 to 1166
15 Nov, 2005
24 Mar, 2008
28 Mar, 2006
-
Contract KC-6CB
Construction of main canal & distribution system earthwork structures & lining of distributaries from RD 1166 to RD 1322
01 Jan, 2006
31 Dec, 2008
08 Nov, 2007
-
Contract KC-6C
Earthwork and Structures of 12 Nos. Distributaries District Dera Bugti
01 Apr, 2007
31 Dec, 2008
30 Aug, 2007
-
KEY ISSUES
Description

NIL

FINANCIAL STATUS 2008-2009
Description A B C D E F
Initial Budget Current Budget Actual Spend to date R/Cost to complete Var. Reason
Fixed
Admn.+ Central Payment 66.394 66.394 21.082 - 45.312 -
Overhead 191.125 191.125 63.750 - 127.375 -
Variable            
Consultants 156.256 156.256 - - 156.256 -
Assets 16.100 16.100 0.004 - 16.095 -
Works 8070.125 8070.125 559.451 - 7510.674 -
Total: 8500.000 8500.000 644.287 - 7855.713 -
Note:- Var. C+D-B = 7855.713 Million
LOCATION MAP Attached