JINNAH HYDROPOWER PROJECT
|
|
Location
The Project is located on the right side of existing
Jinnah Barrage, 5 km from Kalabagh town in District
Mianwali and 234 km from Islamabad. |
 |
|
Scope
of Work |
|
Construction
of 96 MW Hydropower Project |
|
Objectives/Benefits |
|
To produce
mean annual hydroelectricity of 688 GWH. |
|
Date of
Commencement |
|
Project
Commencement
date 18th February 2006 |
|
Date of
Completion |
|
First unit
is expected to be commissioned in December, 2011 and all
the 8 units will be completed upto December 2012. |
|
Project
Cost As Per PC-I |
|
PC-I of
the Project approved on 02-09-2002 for Rs. 13546.8
Million with FEC of Rs. 6608.221 Million. |
|
SALIENT FEATURES |
|
Installed
Capacity
(MW)
|
96 |
|
Gross Head
(m) |
4.88 |
|
Mean Annual
Energy (GWh) |
688 |
|
Design
Discharge (m3 /sec) |
2400 |
|
No.
& Type of Turbine |
8-Pit Type
|
|
Turn Key
Cost (Million US$) |
128 |
|
Implementation Period
(Years) |
4 |
|
PROJECT CONTRACTOR |
|
M/s Dongfang Electric Corporation (DEC) of China. |
|
PROJECT CONSULTANTS |
|
JV of M/s
ACE (Pvt) Ltd. (Lead Partner), M/s NESPAK, M/S NDC, M/s
MWH in association with M/s NESEPAK and M/s DMC. |
|
PRESENT STATUS /PROGRESS |
Physical Progress *92.92%
* The Physical Progress of the Project before the
flooding event was 95.5%. Due to the adverse effects of
the flood, it had been reduced to 77.5%.
|
JINNAH
HPP
The Status of works at Project site is as under.
- Civil Works of Power House, Headrace & Tailrace
Channels are almost completed. M/s DEC have conducted 72
hrs. reliability test at 2200 hrs. on 08.01.2012, but as
per Consultants the same 72 hrs. reliability test will
be conducted again as previously it was not conducted
with maximum generation of 12 MW continuously. The
first unit has also been synchronized with National
Grid. |
|
O&M
Staff Colony |
|
- PC-I for the
construction of O&M staff colony was approved on
19-11-2009 for Rs. 253.07 million.
|
Latest Status
- The sub soil investigation report regarding test pits
at O&M colony site has been sent to CDO (Water) on
31.10.2011 for revised foundation design/drawing of O&M
Staff Colony which is under process. Bore hole
(percussion) of size 18 has been carried out at site by
CMTL on 28.11.2011 for overhead water Tank and detailed
Sub Soil investigation for which report has been sent to
GM (CDO) on 09.01.2012 for revised reliable design of
foundtion of Overhead Tank. |
|
Incharge
of the Project
Engr. Amir
Baksh Mirani, Chief Engineer & Project Director
Jinnah Hydropower Project
Kalabagh Town, District Mianwali
Contact No. 0459-399303
Mobile No. 0300-8005175 |
|
Updated
31-01-2012 |
 |