JINNAH HYDROPOWER PROJECT

Location

The Project is located on the right side of existing Jinnah Barrage, 5 km from Kalabagh town in District Mianwali and 234 km from Islamabad.

Scope of Work
Construction of 96 MW Hydropower Project
Objectives/Benefits
To produce mean annual  hydroelectricity of 688 GWH. 
Date of Commencement 
18th February 2006
Date of Completion 
October, 2013 (Expected).
Project Cost As Per PC-I
PC-I of the Project approved on 02-09-2002 for Rs. 13546.8 Million with FEC of Rs. 6608.221 Million.
SALIENT FEATURES
Installed Capacity  (MW)   96
Gross Head (m) 4.88
Mean Annual Energy   (GWh) 688
Design Discharge (m3 /sec) 2400
No.  & Type of Turbine 8-Pit Type
Turn Key Cost (Million  US$) 128
Implementation Period (Years) 4
PROJECT CONTRACTOR
M/s Dongfang Electric Corporation (DEC) of China.
PROJECT CONSULTANTS
JV of M/s ACE (Pvt) Ltd. (Lead Partner), M/s NESPAK, M/S NDC, M/s MWH in association with M/s NESEPAK and M/s DMC.
PRESENT STATUS /PROGRESS
Physical  Progress 99.59%
UNIT NO.1
The unit is on commercial operation since 31.03.2012.
UNIT NO.2
The unit is on commercial operation since 08.10.2012.
UNIT NO.3
The unit is on commercial operation since 16.08.2012.
UNIT NO.4
The erection of Turbine Components and Generator alignment has been completed and is ready for mechanical/hear run test.
UNIT NO.5
The unit is ready for 72 hours run after completing the mechanical/heat run test.
UNIT NO.6
Welding and painting works of oil/water pipe line and installation Pressure Tank Governor has been completed.
UNIT NO.7
Installation of Governor, runner hub, piping work and fitting of Runner Hub are under progress.
UNIT NO.8
Installation of runner, main shaft has been completed and primary adjustment of axial line is in progress.
O&M Staff Colony
- PC-I for the construction of O&M Staff Colony was approved on 19-11-2009 for Rs. 253.07 million.

Latest Status
 

Chief Engineer & PD (JHP) constituted the Tender Evaluation Committee to evaluate the bids received for the construction of O&M colony. The evaluation has been completed by the committee and submitted their recommendations to CCC, which are under process of review by CCC.

Incharge of the Project
Aziz Ahmad, Chief Engineer & Project Director
Jinnah Hydropower Project
Kalabagh Town, District Mianwali
Contact No. 0092-0459-399303
Mobile No. 0333-4224444

Updated 15-04-2013