|
JINNAH HYDROPOWER PROJECT
|
|
Location
The Project is located on the right side of existing
Jinnah Barrage, 5 km from Kalabagh town in District
Mianwali and 234 km from Islamabad. |
 |
|
Scope
of Work |
|
Construction
of 96 MW Hydropower Project |
|
Objectives/Benefits |
|
To produce
mean annual hydroelectricity of 688 GWH. |
|
Date of
Commencement |
|
18th February 2006 |
|
Date of
Completion |
|
October, 2013
(Expected). |
|
Project
Cost As Per PC-I |
|
PC-I of
the Project approved on 02-09-2002 for Rs. 13546.8
Million with FEC of Rs. 6608.221 Million. |
|
SALIENT FEATURES |
|
Installed
Capacity
(MW)
|
96 |
|
Gross Head
(m) |
4.88 |
|
Mean Annual
Energy
(GWh) |
688 |
|
Design
Discharge (m3 /sec) |
2400 |
|
No.
& Type of Turbine |
8-Pit Type
|
|
Turn Key
Cost (Million US$) |
128 |
|
Implementation Period
(Years)
|
4 |
|
PROJECT CONTRACTOR |
|
M/s Dongfang Electric Corporation (DEC) of China. |
|
PROJECT CONSULTANTS |
|
JV of M/s
ACE (Pvt) Ltd. (Lead Partner), M/s NESPAK, M/S NDC, M/s
MWH in association with M/s NESEPAK and M/s DMC. |
|
PRESENT STATUS /PROGRESS |
Physical Progress 99.59%
UNIT NO.1
The unit is on commercial operation since
31.03.2012.
UNIT NO.2
The unit is on commercial operation since
08.10.2012.
UNIT NO.3
The unit is on commercial operation since
16.08.2012.
UNIT NO.4
The erection of Turbine Components and Generator
alignment has been completed and is ready for
mechanical/hear run test.
UNIT NO.5
The unit is ready for 72 hours run after
completing the mechanical/heat run test.
UNIT NO.6
Welding and painting works of oil/water pipe
line and installation Pressure Tank Governor has been
completed.
UNIT NO.7
Installation of Governor, runner hub, piping work and
fitting of Runner Hub are under progress.
UNIT NO.8
Installation of runner, main shaft has been
completed and primary adjustment of axial line is in
progress. |
|
O&M
Staff Colony |
|
- PC-I for the
construction of O&M Staff Colony was approved on
19-11-2009 for Rs. 253.07 million.
|
|
Latest Status
Chief Engineer & PD (JHP) constituted the Tender
Evaluation Committee to evaluate the bids received for
the construction of O&M colony. The evaluation has been
completed by the committee and submitted their
recommendations to CCC, which are under process of
review by CCC. |
|
Incharge
of the Project
Aziz Ahmad, Chief Engineer & Project Director
Jinnah Hydropower Project
Kalabagh Town, District Mianwali
Contact No. 0092-0459-399303
Mobile No. 0333-4224444 |
|
Updated
15-04-2013 |
 |