JINNAH HYDROPOWER PROJECT
Updated as on 15.04.2014

Location

The Project is located on the right side of existing Jinnah Barrage, 5 km from Kalabagh town in District Mianwali and 234 km from Islamabad.
Scope of Work
Construction of 96 MW hydropower project
Objectives/Benefits
To produce mean annual hydroelectricity of 688 GWh.
Date of Commencement 

18th  February 2006

Date of Completion 
October, 2013 (Expected).
Project Cost As Per PC-I
PC-I approved by ECNEC on 29.02.2002 for Rs.13546.8 Million with FEC of Rs.6608.221 Million.
SALIENT FEATURES
Installed Capacity  (MW)   96
Gross Head (m) 4.88
Mean Annual Energy   (GWh) 688
Design Discharge (m3 /sec) 2400
No.  & Type of Turbine 8-Pit Type
Turn Key Cost (Million  US$) 128
Implementation Period (Years) 4
PROJECT CONTRACTOR & CONSULTANTS
M/s Dongfang Electric Corporation (DEC) of China.
PROJECT CONSULTANTS
JV of M/s ACE (Pvt) Ltd. (Lead Partner), M/s NESPAK, M/S NDC, M/s MWH in association with M/s NESEPAK and M/s DMC.
Present Status/Progress
Physical Progress                                99.97%.
 

The Project Status is as under:-

 

UNIT NO.1

The Unit is under commercial operation since 31.03.2012.

 

 UNIT NO.2

The Unit is under commercial operation since 08.10.2012.

UNIT NO.3
The Unit is under commercial operation since 16.08.2012.


UNIT NO.4
The Unit is under commercial operation since 17.06.2013.

UNIT NO.5

The Unit is under commercial operation since 16.05.2013.


UNIT NO.6
The Unit is under commercial operation since 14.10.2013.


UNIT NO.7

The Unit is under commercial operation since 14.10.2013.


UNIT NO.8

The Unit is under commercial operation since 07.09.2013.


Status of Punch List Items:
Rectification  of pending punch list item is underway and being attended by M/s
DEC as manpower for allied works have been arrived on.

 

Financial Progress:                        15.00%

Being an EPC Contract only mobilization advance of 15% has been paid to the contractor, Rest 85% will be arranged under supplier’s credit by the Contractor.


O&M Staff Colony

The construction work of O&M colony at Jinnah Hydropower Project is under progress. The percentage completion progress of different works of O&M colony is as follows:

 

Overall Progress:                          40.16%

 

  • General Items                                46%
  • Pre-constriction treatment                78%
  • 20-Bed Hostel                                60%
  • Category-II Residences                   62%
  • Category-III Residences                  50%
  • Category-IV Residences                   40%
  • Category-V Residences                    35%
  • Mosque                                          25%
  • High School                                     70%
  • Boundary Wall                                 85%
  • 04 Bed Rest House                          25%
  • Recreation Center                            5%
  • Dispensary                                      20%
  • Overhead Tank                                5%

Incharge of the Project
Nisar Ahmed Memon
Chief Engineer & Project Director,
Jinnah Hydropower Project,
Kalabagh Town, District Mianwali
Contact No. 0092-459-399303
Cell No.       0333-4224444