JINNAH HYDROPOWER PROJECT

Location

The Project is located on the right side of existing Jinnah Barrage, 5 km from Kalabagh town in District Mianwali and 243 km from Islamabad.

SALIENT FEATURES
Installed Capacity  (MW)   96
Annual Energy   (GWh) 688
Design Discharge (m3 /sec) 2800
Average Head (m) 4.8
No. of Units 8
Turn Key Cost (mill. US$) 128
Implementation Period (Years) 4
PRESENT STATUS  

 

§           Feasibility Study updated by WAPDA-GTZ in April 2000.

§           PC-I of the Project approved on 02.09.2002 for Rs.13546.8 Million with FEC of   Rs.6608.221 Million.

§           After series of discussions with Dong Feng Electric Company (DEC) of China, project cost finalized as US$ 128 million. 

§           On the basis of Sovereign Guarantee issued by Ministry of Finance (GOP), amended the Contract as agreed upon signed between WAPDA and DEC of China on 23rd November, 2005.

§           The project is being implemented on EPC/Turnkey basis with Supplier’s Credit arranged by M/s. Dongfang Electric Corporation, China.

§           15% mobilization advance given to the Contractor. Contractor mobilized on site in February, 2006.

§           Project commencement date               February, 2006
 

§           Project completion date                      February, 2010

PROGRESS
Physical                       45.80% as on 30.06.2008
Financial                      EPC Contract

Temporary Works Completed
PERMANENT WORKS

POWER HOUSE

Cutoff Curtain Completed
Dewatering
a.  Drainage Channels Completed
b.  Drilling and Installation of Wells Completed
c.   Installation of Pumps Completed
Excavation 
a.  Powerhouse Pit 100%
b.  Headrace Channel 69.3%
c.   Tailrace Channel 85%
Concreting
a. Blinding concrete completed in various sections of unit 1 to 8.
b. Structural concrete started in various sections of unit 1 to unit 8.