GOLEN GOL HYDROPOWER PROJECT

Location

The project is located on Golen Gol Mullah, a tributary of Mastuj River, 25 Km from Chitral Town in KPK.
 

SCOPE OF WORK
Construction of O&M Staff Colony (Lot-1) Civil Work (Lot-2) Civil Works of power House (Lot-3.1) E&M Works (Lot-3.2) and Transmission Line (Lot-4)
OBJECTIVES / BENEFITS
To Generate 106 MW Hydel Electricity
DATE OF COMMENCEMENT

As Per PC-I

Revised

July 2002

February 2011

DATE OF COMPLETION
As Per PC-I Expected
June 2006 February 2015
PROJECT COST AS PER PC-I / PC-II Rs. 7035.128 Million
SALIENT FEATURES
Installed Capacity MW 106 MW
Annual Energy GWH 436
Design Discharge 30 m3/sec
Tunnel Length 3.8 KM
Design Head 435 M
PRESENT STATUS / PROGRESS
  • LOT-1 COLONY

                Date of Commencement       February  2009
                Date of completion              Febrauary 2011

    O&M Wapda staff colony at Koghuzi Chitral is substantially completed.

    LOT-2 & 3.1

    The civil work Contracts (Lot-2 & 3.1) have been alloted to M/s SAMBU SARCO JV date of commencement for the contract was 01.02.2011. Contractors have been mobilized to site and following site activities are completed/in progress.

    • Batching/crushing plant near powerhouse site is completed & functional.

    • Batching plant at weir site completed and functional.

    • Construction of 1st and 2nd Cement warehouse completed and functional.

    • Access Raod to Surge chamber - Excavation partially completed from RD 0+000 - 3+738.

    • Assess Raod to Weir site - Excavation partially Completed from RD 0+000 - 5+725.

    • Access Tunnel to Prussure tunnel - Excavation comleted from Ch.0+000 to  0+064.8m.

    • Access Tunnel to Headrace tunnel - Site cleared for benching.

    • Aeration Tunnel - excavation for 1st and 2nd bench completed &3rd is in progress.

    • Headrace Tunnel Portal - Excavation for 1st, 2nd 3rd bench completed.

    • Headrace Tunnel -Excavation completed from ch.0+000 to 0+0024 m.

    • Construction of the 1st, 2nd 3rd and 4th Gabion wall at right side of inlet Portal for Headrace tunnel and Construction of 1st, 2nd and 3rd at left side are completed Construction of Gabion wall at Elevation 2043.5 m on both side of inlet portal for Headrace tunnel is in progress.

    • Sand Trap - Excavation for 1st 2nd & 3rd bench is completed and 4th bench is in progress.

     

    Concrete Work:
    (a) Section 2-2

    Description Concrete (G25) Quantity poured (m3) Remarks
    Block 1 274.8 Retaining wall Pad
    Block 2 274.8 Retaining wall Pad
    Block 1 & 2 135.7 Retaining wall Pad, stage 1
    Block 1 & 2 149 Retaining wall Pad, stage 1

    (b) Section 3-3

    Description Concrete (G25) Quantity poured (m3) Remarks
    Block 1 356 Retaining wall Pad
    Block 2 151 Retaining wall Pad, stage 1
    Back filling   Back filling is in progress (30 cm layer)

    (b) Section 3-3

    Description Concrete (G25) Quantity poured (m3) Remarks
    Block 1 296 Retaining wall Pad
    Block 2 357 Retaining wall Pad

    LOT- 3.2 E & M Works

    Tenders for Lot-3.2 (E&M Works) opened on 30.06.2011. and awarded to M/s Rainpower-Alstom Grid-Indar - Al-Fajr international.

    LOT-4 Transmission Line

    After authority has decided to invite bid on post qualification basea, the bid submission date for LOT-4 extended up to July 4, 2012

    9- Consultancy agreement for construction supervision has been signed, the consultant have been mobilized at site.

Incharge of the Project

Mr. Khan Muhammad
Project Director
Golen Gol Hydropower Project WAPDA Chitral
Phone No.0943-316497

Updated as on 06.06.2012