GOLEN GOL HYDROPOWER PROJECT

Location

The project is located on Golen Gol Nullah, a tributary of Mastuj River, 25 Km from Chitral Town in Khyber Pakhtunkhwa.

SCOPE OF WORK
Construction of O&M Staff Colony LOT-1 Civil Work Lot-2 Civil Works of power House Lot-3.1 E&M Works Lot-3.2 and Transmission Line Lot-4
OBJECTIVES / BENEFITS
To Generate 106 MW Hydel Electricity
DATE OF COMMENCEMENT

As Per PC-I

Revised

July 2002

February 2011

DATE OF COMPLETION
As Per PC-I Expected
June 2006 February 2015
PROJECT COST AS PER PC-I / PC-II Rs. 7035.128 Million
SALIENT FEATURES
Installed Capacity MW 106
Annual Energy GWH 436
Design Discharge 30 m3/sec
Tunnel Length 3.8 KM
Design Head 435 M
PRESENT STATUS / PROGRESS
  • LOT-1 COLONY

    O&M Wapda staff colony at Koghuzi Chitral is substantially completed.

    LOT-2 & 3.1 Civil Works /Power House
    The civil work contractrs (Lot-2 & 3.1) have been alloted to M/s SAMBU SARCO JV date of commencement for the contract was 01.02.2011. Contractors have been mobilized to site and following site activities are completed/in progress.

    • Batching/crushing plant near powerhouse site is completed & functional.

    • Batching plant at weir site completed and functional.

    • Demarcation for downstream & upstream wing wall & second diversion channel has been done.

    • Excavation is in progress for upstream wing wall.

    • Rock bolts installation on portal face is in progress.

    • Construction of Access road to surge chamber is in progress.

    • First cement warehouse completed and construction of second is in progress.

  • LOT 3.2 E&M Works
    Tenders for Lot-3.2 (E&M Works) opened on 30.06.2011. Work will be awarded shortly.

  • LOT-4 Transmission Line
    After authority has decided to invite bid on post qualification basis, the amended bidding documents (post qualification basis) has been sent to the OFID for seeking concurrence which is still awaited..

  • Consultancy agreement for construction supervision has been signed, the consultant have been mobilized at site.

Incharge of the Project

Mr. Ishtiaq Anwar
Project Director
Golen Gol Hydropower Project WAPDA Chitral
Phone No.0943-413473 Chitral
091-9212041-47 Ext. 325 Peshawar

Updated as on 29.02.2012