DUBER KHWAR
HYDROPOWER PROJECT |
|
Location
|
The Project is
located on Duber Khwar River, a tributary of Indus River near Pattan,
District Kohistan in N.W.F.P. at a distance of 265 Km from Islamabad. |
|
Brief scope of the Project
|
|
Installed Capacity
|
130 MW |
|
Design Discharge |
29 m3/s |
|
Gross Head |
535 m |
|
Pressure Tunnel |
4.872 Km |
|
Energy per annum |
595 GWh |
|
Main Components
|
Reservoir Weir Pressure
Tunnel Powerhouse Tailrace Switchyard |
|
Approving Agency |
ECNEC |
|
Date of approval
|
02.09.2002 |
|
Approval cost of Project
|
|
Local |
Foreign |
Total |
|
5606.750 |
4147.510 |
9754.260 |
|
Date of Commencement |
|
Original (as per Contract) |
Revised |
|
Jul 2003 |
|
|
Date of Completion |
|
Original (as per Contract) |
Revised |
|
Oct. 2008 |
Jul 2010 / Oct. 2010 |
|
Progress |
|
A-FINANCIAL
|
Local |
Foreign |
Total |
|
(i) |
Expenditure upto
30.06.2008 |
3444.590 |
1492.215 |
4936.805 |
|
(ii) |
Budget allocation 2008-09 |
1930.000 |
1570.000 |
3500.000 |
|
(iii) |
Exp during current
Financial year (upto 31 Aug 2008 ) |
82.886 |
58.001 |
140.887 |
|
(iv) |
Expenditure upto date (i+iii) |
3527.886 |
1550.216* |
5077.692 |
|
B-PHYSICAL (upto Aug 2008) |
Planned (%) |
Actual (%) |
|
(i) |
Civil Works |
61 |
43.50 |
|
(ii) |
E&M |
91 |
42 |
|
* Expenditure
incurred against Foreign Component has been met out of Cash Foreign
Exchange. |
|
Reason for Delay
|
- Late issuance of
Construction Order (05 Oct. 2005) due to delay in completion of
access roads.
- Effects of
devastating earthquake of 8th Oct. 2005 in form of frequent slides
on Thakot-Allai road & project sites resulting form after shocks.
- Scarcity of local
labour in the area after earthquake.
- Adverse climatic
conditions.
- Slow progress due
to poor management of Chinese Contractor.
- Evacuation of
Chinese from Project sites due to security reason on 07 Nov 2007.
Resumption of Works at Project sites with effect from 18 Apr. 2008.
|