|
-
06 Nos. Micro-Seismic Stations have been
established in the project area.
- River bed drilling,
one bore hole about 51 meter deep had been completed at
U/S Coffer Dam Site during the
March, 2011.
- Steering Committee
of WCAP has approved US$ 8.0 million on October, 2011
for detailed Engineering Design
and Tender
Documents & Tendering of Dasu HPP.
-
The Consultancy Contract Agreement for preparation and
Implementation of Dasu Hydropower Project has been
signed on September 19, 2011 between Dasu Hydropower
Consultant and WAPDA.
- Dasu
Hydropower Consultant (DHC) was mobilized and commenced
their services from September 19, 2011.
- Kick of
meeting with Dasu Hydropower Consultant (DHC)
was held on September 24, 2011 in the office of Project
Director Dasu HPP.
- Mr. Masood Ahmad,
Task Leader, World Bank along with Mr. Muhammad Saqib,
Sr. Energy specialist and Mr.
Anjum Ahmad,
Sr. Energy & PPP Specialist visited DHC office, Lahore
and hold meeting with and Mr. Anjum
Ahmad, Sr.
Energy & PPP Specialist visited DHC office , Lahore and
hold meeting with DHC and Project Director,
Dasu HPP and
his team. During meeting Project scheme was discussed in
detail.
- DHC has
submitted invoices for Advance of Pakistan Rupee
portion, Euro Portion and Japanese Yen Portion along
with the Bank
Guarantees. After approval from General Manager (Hydro)
Planning, the invoices have been
forwarded to
General Manager (C&M) Water, WAPDA for further
processing.
- PD (Dasu) Field
Office has been established at Dasu Town District
kohistan since November 2011.
- Inception Report of
Dasu Hydropower Project was received from DHC on
November 29, 2011. |