|
PROJECT
CONSULTANTS
JV of M/s
Mott MacDonald Ltd (Lead Partner) M/s Sogreah M/s
Nippon Koei Co Ltd M/s MM Pakistan (Pvt) Ltd and M/s DMC.
PRESENT STATUS / PROGRESS
· Feasibility
report has been submitted by the Consultants on 31 March
2009.
.
Draft detailed design report and Tender Documents of
different lots have been submitted by the Consultants,
which are under review by different quarters.
.
Suspended sediment samples at Gainji Bridge, Kachura
Alam Bridge and Bunji Bridge have been collected and
analyzed by ISRIP, WAPDA, as recommended by POE Upto
September 2011.
.
Drilling in dam and powerhouse areas at new structure
location is in progress by DID, WAPDA, Lahore. Upto date
11614.2m drilling has been completed against 13610.0m.
Installation of Piezometers and inclonometers in some of
the boreholes at shengua area is in progress.
.
Model studies for four models: Sectional Model of spillway,
Comprehensive Model of Dam Area,, low and Mid Level outlet
and Tailrace outlet models have been constructed. All
tests proposed by Consultants and POE have been
performed and presently no further tests are foreseen.
. 4 No. Exploratory Adits at dam area have been completed
and preparation for performing plate load tests by CMTL
WAPDA is in
progress.
.
Exploratory Adit to Fault Zone (Package-2) as
recommended by POE would be taken up as advance Package
to main construction contract and its cost would be
covered in the PC-I.
.
The work for excavation of Exploratory Adit for under
ground Power house (Package-3) has been awarded to M/s
High Technology Engineering Company, Islamabad. Contract
agreement has been signed on 07.07.2011. Contractor has
mobilized on site and excavation work is in progress.
.
The work for excavation of Exploratory Adit for power
shaft (Package-4) has been awarded through retendering
process to M/s High Technology Engineering Company,
Islamabad. Contract Agreement has been signed on
16.11.2011. Contractor has been mobilized and
preliminary works for construction of Adit to surge area
is in Progress.
.
Bunji Consultants (JV) is to complete the design report,
preparation of tender documents and PC-I considering the
completed and ongoing investigations upto September 30,
2012.
Incharge
of the Project
Engr. Hasnain Afzal
General Manager (Hydro) Planning
WAPDA Sunny View Lahore.
Contact No. 0092-42-99202717
Mobile No. 0092-0300-8411244
|