ALLAI KHWAR
HYDROPOWER PROJECT |
|
Location
|
The Project is
located on Allai Khwar River, a tributary of Indus River near Besham
District Battgram in N.W.F.P. at a distance of 245 Km from Islamabad. |
|
Brief scope of the Project
|
|
Installed Capacity
|
121 MW |
|
Design Discharge |
21 m3/s |
|
Gross Head |
687 m |
|
Pressure Tunnel |
2.366 Km |
|
Energy per annum |
463 GWh |
|
Main Components
|
Reservoir Weir Pressure
Tunnel Powerhouse Tailrace Switchyard |
|
Approving Agency |
ECNEC |
|
Date of approval
|
02.09.2002 |
|
Approval cost of Project
|
|
Local |
Foreign |
Total |
|
5124.284 |
3453.540 |
8577.823 |
|
Date of Commencement |
|
Original (as per Contract) |
Revised |
|
June 2003 |
|
|
Date of Completion |
|
Original (as per Contract) |
Revised/Expected |
|
June 2007 |
Jan 2009 / Sep 2010 |
|
Progress |
|
|
A-FINANCIAL
|
Local |
Foreign |
Total |
|
(i) |
Expenditure upto
30.06.2008 |
2784.490 |
1145.360 |
3929.850 |
|
(ii) |
Budget allocation 2008-09 |
1685.000 |
580.000 |
2535.000 |
|
(iii) |
Exp during current
Financial year (upto 30 Sept. 2008 ) |
124.656 |
129.656 |
254.312 |
|
(iv) |
Expenditure upto date (i+iii) |
2909.146 |
1275.016* |
4184.162 |
| |
|
|
|
|
|
B-PHYSICAL (upto Sept. 2008) |
Planned (%) |
Actual (%) |
|
(i) |
Civil Works |
92 |
29 |
|
(ii) |
E&M |
95 |
42 |
|
* Expenditure
incurred against Foreign Component has been met out of Cash Foreign
Exchange. |
|
Reason for Delay
|
- Late issuance of
Construction Order (06 August 2005) due to delay in completion of
access roads.
- Effects of
devastating earthquake of 8th Oct. 2005 in form of frequent slides
on Thakot-Allai road & project sites resulting from after shocks.
- Scarcity of local
labour in the area after earthquake & NGOs operation.
- Adverse climatic
conditions.
- Slow progress due
to poor management of Chinese Contractor.
- Evacuation of
Chinese from Project sites due to security reason on 7 Nov. 2007.
Resumption of Works at Project sites with effect from 20 Feb. 2008.
|