RBOD-I
Print this page

RBOD-I

Location :  Larkana, Kamber-Shahdadkot, Dadu & Jamshoro Districts of Sindh Province.
Scope Of Work: To provide outfall facilities to existing & proposed drainage projects to improve environmental conditions in Manchar & Hamal Lakes.Rehabiliation of existing drainage system. This work will also increase agricultural production in an area of 1.28 Million acres. 
Executing Agency                                                          WAPDA
Contractor
  • M/s Khyber Grace (Private) Ltd., M/s Malik Riaz & Company, M/s Abrar Malik & Company, M/s S.H Haq Noor & Company (Private) Ltd, M/s Muhammad Ayub & Brothers (Private) Ltd, M/s Al-Raee Construction Company (Private) Ltd & Marathon Construction Co. (Private) Ltd (JV),
  •  M/s Ramzan & Sons (Pvt.) Ltd, (for Balance Work).
  •  M/s Balochistan Engineering Work.
Consultant
  • M/s National Development Consultants & EASE-PAK (J.V) (Consultancy Agreement expired on 31.12.2010).
  • M/s G3 Engineering Consultants (Pvt.) Ltd Lahore for Balance work of the Project.
Commencement Date (Phase-1) July 1994
Completion Date (Phase-1) Nov 2019
Financial Status (Rs. Million) Local Foreign Total
Original PC-I (18.09.1994) 2,532.000 1,863.000 4,395.00
1st Revised PC-I Cost (30.11.2006) 14,707.143 - 14,707.143
2nd Revised PC-I Cost (26.07.2017) 17,505.018 - 17,505.018
PSDP Allocation for 2018-2019 1000.00 - 1000.00

 

Status 

  • Scope of work increased due to inclusion of Remodelling of Main Nara Valley Drain (MNVD) of Contract R-III(a/1), R-III(a/2), R-III(a/3) and Balance work of IL-1, IL-2, IL-3 from works under RBOD-I.
  • Extension of RBOD upto MKZP-Contract No. RI(A). WAPDA Authority accorded approval to release the Contractor from further performance of Contract. Upto date Progress is 85.60%.
  • Widening of IL-2&3 for 3,500 cusecs – Contract No. RI (B). WAPDA Authority accorded approval to release the Contractor from further performance of Contract. Upto date Progress is 87.03%.
  • Balance work of IL-1 widening for 3,500 cusecs – Contract No. RI (E). WAPDA Authority accorded approval to release the Contractor from further performance of Contract. Upto date Progress is 81.91%.
  • Remodelling of MNVD RD 110+000 – Contract No. RIII (a/3). WAPDA Authority accorded approval to release the Contractor from further performance of Contract. Upto date Progress is 63%.
  • Balance Work of Remodelling of MNVD (RD 0 To 110) and construction of additional structures from RD 110 to 220. Contract awarded to the lowest bidder M/s Hasas – Tameer Associates JV.
  • Balance work of RBOD Extension (MNVD) i/c additional structures from RD 00 to RD 132+600 & from RD 220 to RD 342+ of MNVD. Contract awarded to the lowest bidder M/s Balochistan Engineering Work, Quetta
  • Monitoring of Quality of Effluent of Project Area. Work is being carried out through Surface Water Hydrology Project WAPDA as deposit work.

         

          Physical Progress 85%

 

Incharge of the Project

           Mr. Mukesh Kumar

           Project Director

           RBOD-I Project