LOWER INDUS RIGHT BANK IRRIGATION & DRAINAGE PROJECT (RBOD-I)
 

LOWER INDUS RIGHT BANK IRRIGATION & DRAINAGE PROJECT (RBOD-I)

Location
Larkana, Kamber-Shahdadkot, Dadu & Jamshoro Districts of Sindh Province
Scope of Work

To provide out-fall facilities to existing & proposed drainage units including rehabilitation of existing drainage network and to improve environmental conditions in Manchar & Hamal Lakes. This work will also increase agricultural production and improve environmental conditions in an area of 1.278 Million Acres.

 rbod1
Executing Agency WAPDA
Contractors

Previous:

M/s Khyber Grace (Private) Ltd Islamabad, M/s Malik Riaz & Company Lahore, M/s Abrar Malik & Company Lahore, M/s S.H Haq Noor & Company (Private) Ltd,M/s Muhammad Ayoub & Brothers (Private) Ltd, M/s Al-Raee Construction Company (Private) Ltd & Marathon Construction Co.(Private) Ltd (JV), M/s MRCL, Karachi.

Present:

M/s Ramzan & Sons (Pvt.) Limited

M/s Hasas – Tameer Associates (J.V)

Consultants

Previous:

M/s National Development Consultants & EASE-PAK (J.V)

Present:

M/s G3 Engineering Consultants (Pvt.) Ltd Lahore in association with BM Consulting Engineers.

Commencement Date July, 1994
Completion Date March, 2020
2nd Revised PC-I Rs. 17,505.018 Million (Approved by ECNEC on 26.07.2019)
PSDP Allocation for 2019-2020 Rs. 1,321.780 Million

Completed Works:

  1. Construction of Indus Link and Structures
  2. Construction of Extension of RBOD upto Miro Khan Zero Point (MKZP)
  3. Remodelling of Main Nara Valley Drain (MNVD) for 3500 cusecs
  4. Construction of New Hamal Regulator at Hamal Lake.
  5. Rehabilitation of Rato Dero Pump Station.

Balance Works in progress:

  1. Remodelling of Indus Link & Construction of Structures – Substantially Completed
  2. Remodelling of Existing Main Nara Valley Drain (MNVD) and Additional Structures. The Contractor has commenced the work w.e.f. 11.04.2019. Upto date Progress is 55%.  
  3. Remaining works on Extension of Main Nara Valley Drain (MNVD) and Additional Structures. The Contractor has mobilized at site and work is in progress. Upto date Progress is 15%. 

Overall Physical Progress                 90.23%          

Incharge of the Project

Engr. Mukesh Kumar
Project Director
RBOD-I Project
Contact No. 0092-71-9310449