LOWER INDUS RIGHT BANK IRRIGATION & DRAINAGE PROJECT (RBOD-I)
English Chinese (Simplified) Urdu

LOWER INDUS RIGHT BANK IRRIGATION & DRAINAGE PROJECT (RBOD-I)

Location
Larkana, Kamber-Shahdadkot, Dadu & Jamshoro Districts of Sindh Province
Scope of Work

To provide out-fall facilities to existing & proposed drainage units including rehabilitation of existing drainage network and to improve environmental conditions in Manchar & Hamal Lakes. This work will also increase agricultural production and improve environmental conditions in an area of 1.278 Million Acres.

 rbod1
Executing Agency WAPDA
Contractors

Previous:

M/s Khyber Grace (Private) Ltd Islamabad, M/s Malik Riaz & Company Lahore, M/s Abrar Malik & Company Lahore, M/s S.H Haq Noor & Company (Private) Ltd, M/s Muhammad Ayoub & Brothers (Private) Ltd, M/s Al-Raee Construction Company (Private) Ltd & Marathon Construction Co.(Private) Ltd (JV), M/s MRCL, Karachi.

Present:

M/s Ramzan & Sons (Pvt.) Limited

M/s Hasas – Tameer Associates (J.V)

Consultants

Previous:

M/s National Development Consultants & EASE-PAK (J.V)

Present:

M/s G3 Engineering Consultants (Pvt.) Ltd Lahore in association with BM Consulting Engineers.

Commencement Date July 1994
Completion Date June 2020
2nd Revised PC-I Rs. 17,505.018 Million (Approved by ECNEC on 26.07.2019)
PSDP Allocation for 2019-2020 Rs. 1,321.780 Million

Completed Works:

  • Construction of Indus Link and Structures
  • Construction of Extension of RBOD up to Miro Khan Zero Point (MKZP)
  • Remodeling of Main Nara Valley Drain (MNVD) for 3500 cusecs
  • Construction of New Hamal Regulator at Hamal Lake.
  • Rehabilitation of Rato Dero Pump Station.

Balance Works in progress:

  • Remodeling of Indus Link & Construction of Structures – Substantially Completed
  • Remodeling of Existing Main Nara Valley Drain (MNVD) and Additional Structures. The Contractor has commenced the work w.e.f. 11.04.2019. Upto date Progress is 71%.
  • iii. Remaining works on Extension of Main Nara Valley Drain (MNVD) and Additional Structures. The Contractor has mobilized at site and work is in progress. Up to date, Progress is 57%.

Overall Physical Progress 94.62%

Incharge of the Project

Engr. Mukesh Kumar
Project Director
RBOD-I Project
Contact No. 0092-71-9310449