Darawat Dam Project

Location: Across Nai Baran and about 70 Km West of Hyderabad and 135 Km North East of Karachi.
Salient Features
Dam Type Concrete Gravity Dam
Height of Dam 46 meter
Gross Storage Capacity 121,605 AF
Live Storage Capacity 89,192 AF
CCA 25,000 Acres
Power Generation 0.3 MW (will be developed under PPP mode)
Execution by WAPDA 
Supervision Consultants M/s National Development Consultants & M/s CAMEOS (Joint Venture)      
Contractor M/s Sinohydro Corporation Ltd.
Donor Agency Govt: of Pakistan
Commencement Date 30.06.2010
Completion Date 31.08.2014
Financial Status Local (Rs. Million) FEC (Rs. Million) Total (Rs. Million)
Original PC-I Cost (03.09.2009) 3,175.000 - 3,175.000
1st Revised PC-I Cost (16.08.2012) 9,300.000 - 9,300.000
2nd Revised PC-I Cost (16.08.2012)

11,767.000 submitted to Planning Development and Reforms Division on 09-03-2016 for obtaining approval from ECNEC. The same has been returned to M/o W&P on 07/06/2016 and now it is pending with M/oWP

1,980.050 11,767.870 
PSDP Allocation 2016-2017 1,000.000 - 1,000.000

 

Status:  Project completed in August 2014 and now it is in DNP which will expire on 31.08.2017

 

Incharge of the Project: Muhammad Iqbal Shaikh, Project Director