RBOD-I

DRAINAGE PROJECT RBOD-I

Location: RBOD-I Project is an integral part of Right Bank Outfall Drainage System which has been proposed mainly as a means of disposing of effluent from the Right Bank of Sukkur and Guddu Barrage Commands in Sindh Province. The area benefited under the project is 1.28 Million (Acres (GCA) and major part of the project area lies within the districts of Larkana, Kamber-Shahdadkot, Dadu & Jamshoro Districts of Sindh Province). 
Scope of work: To provide outfall facilities to the existing and proposed drainage project, to improve environmental conditions in Manchhar and Hamal Lakes.Rehabilitation of existing Drainage System. The works includes:
  • Balance work of IL-1 i/c widening for 3500 Cusecs – Contract No. RI(E)
  • Widening of IL-2&3 for 3500 cusecs – Contract No. RI(B)
  • RBOD Extension upto MKZP – Contract No. RI(A)
  • Remodeling of MNVD RD 220+000 to RD342+000 – Contract No. RIII(a/1)
  • Remodeling of MNVD RD 110+000 RD 220+000 – Contract No. RIII(a/2)
  • Remodeling of MNVD RD 0+000 to RD 110+000 – Contract No. RIII(a/3)
  • Balance works of RTD-1A – Contract No. RTD-1(B)
  • Construction of New Hamal Regulator at RD 342 + of MNVD – Contract No. RIII(a/4)

 

Salient Features
EIRR 19.3%
Executing Agency WAPDA
Consultants M/s NDC & EASE-PAK (Joint Venture), the Consultancy Service were expired on 31.12.2010.
Contractor

 M/S Khyber Grace (Private) Limited Islamabad.

 M/s Malik Riaz & Company Lahore.

 M/s Abrar Malik & Company Lahore.

 M/s S.H Haq Noor & Company (Private) Limited.

 M/s Muhammad Ayoub & Brothers (Private) Limited.

 M/s Al-Raee Construction Company (Private) Limited & Marathon Construction Co. (Private) Limited ( Joint Venture)

 

Commencement Date July 01,1994
Completion Date 30.11.2019 (Revised)
Financial Status  Local (Rs. Million) FEC (Rs.Million) Total (Rs. Million)
Approved Original PC-I Cost  4,395.000 - 4,395.000
Approved 1st revised PC-I Cost  14707.143 - 14707.143
2nd Revised PC-I Cost  17,505.018  Cleared by CDWP on 29.11.2016 for approval of ECNEC
PSDP Allocation 1,500.000 - 1,500.000

 

Status:

Description Progress Remarks
Indus Link Widening and Construction.

Balance work of IL-1 including its widening from RD 0+000 to 22+017

Contract No. R1(E)

81.91%

The Authority accorded approval to release the Contractor from further performance of Contract on July, 2011.

Widening of IL-2 & IL-3 for 3500 Cusec from RD 22+017 to 80+282

Contract No. R1(B).

87.03%

The Authority accorded approval to release the Contractor from further performance of Contract on July, 2011.

Extension of RBOD Up to Miro Khan Zero Point.
Extension to MKZP from RD 0+000 to 132+600 85.60%

The Authority accorded approval to release the Contractor from further performance of Contract on July, 2011.

Remodeling of MNVD for 3500 Cusecs drainage effluent.

Remodeling of MNVD from RD 220+000 to 342+220.

Contract No. R-III(a/1).

100%

Taking Over Certificate and Defect Liability Certificate (DLC) approved by the Authority and issued to the Contractor.

Remodeling of MNVD from RD110+000 to 220+000.

Contract No. R-III(a/2).

100%

Taking Over Certificate and Defect Liability Certificate (DLC) approved by the Authority and issued to the Contractor.

Remodeling of MNVD from RD 000+000 to 110+000.

Contract No. R-III(a/3).

63%

The Authority accorded approval to release the Contractor from further performance of Contract on July, 2011.

Balance work of Rato Dero Pump Station - Contract No. RTD-(B).

100%

Work has been completed and handed over to Provincial Irrigation Department GoS on 15.02.2016.

New Hamal Regulator at RD 342 of MNVD – Contract No. RIII(a/4).

100%

Work has been completed and handed over to Provincial Irrigation Department GoS on 16.07.2015.

 

Incharge of the project:

          Engr. Muhammad Ahtesham-ul-Haq

          Project Director