Murunj Dam Project
English Chinese (Simplified) Urdu

Murunj Dam Project

Location
The Project is proposed across Kaha Nullah at about 116 km West of District Rajanpur.
Salient Features
  • Type of Dam

Earth Core Rock Fill  
  • Height of Dam

107 ft.
  • Gross Storage

0.80 MAF
  • Live Storage

0.60 MAF
  • GCA  

120,000 Acres
  • Power Generation

12 MW

Scope of Work

Feasibility Study, Detailed Engineering Design and Preparation of Tender Documents

Execution by

WAPDA

Donor Agency

Govt. of Pakistan

Commencement Date

-

Completion Date

-

Financial Status (Rs. Million)

Local Foreign Total

Approved PC-I Cost (03.09.2009)

349.956 - 349.956

PSDP Allocation for 2021-2022

254.236 - 254.236

Status:-

  • WAPDA Authority in its meeting held on April 24, 2020 accorded approval to award contract for Consultancy Services to M/s NESPAK - JV. Contract Agreement signed between WAPDA and      M/s NESPAK-JV on 20.05.2020.
  • Topographic Survey of Darrah site (Barrage Site), Mud Kund site (Dam site) and reservoir area completed.
  • Geotechnical investigations & Geological mapping at Darrah site completed.
  • Geotechnical investigations & Geological mapping at Mud Kund site in progress.
  • Flow & sediments measurements at Darrah Site are being carried out by SWHP, WAPDA.
  • Collection of soil and water samples from command area has been completed.
  • The Consultants have surveyed for barrow areas for riprap, coarse & fine aggregates for further investigation and tests.
Incharge of the Project      
Engr. Muhammad Abid Sheikh
General Manager (Hydro) Planning
Contact No. 0092-42-99202717

 

 