Tarbela 4th Extension Hydropower Project

 

Location: Tarbela Dam Project, Tehsil Ghazi, District Haripur, Khyber Pakhtunkhwa.
Salient Features
Scope of Work Modification of Tunnel-3 & 4 Intakes and Construction of Powerhouse
Power Generation

Installed Capacity:                           1410 MW

Annual Energy Generation:             3840 GWh

Execution by WAPDA
Supervision Consultants Tarbela 4th Consultant Joint Venture, a Joint Venture of Mott MacDonald (UK) and Coyne et Bellier (France) in Association with MM Pakistan and ACE Pakistan
Contractor

Civil Works Contractor: M/s Sinohydro Group of China

E&M Work Contractor: Consortium of M/s Voith Hydro of Germany & China.

Donor Agency

World Bank:             US$ 840 Million

WAPDA:                     US$ 74 Million

Commencement Date 28.10.2013
Completion Date

14th August 2017 (Unit 17)

 

Financial Status Local (Rs. Million) FEC (Rs. Million) Total (Rs. Million)
Original PC-I Cost 17,735.668 65,865.368 83,601.036
PSDP Allocation Fy 2016-17 5700.000 10,787.000 16487.000

 

 Environmental Initiatives 

           TARBELA 4TH EXTENSION HYDROPOWER PROJECT

 Status:

           Physical Progress is 68.54 %

 Incharge of the Project:

            Sohail Khan

            CE/PD, T4thHP, Old HPD Building

            Project Office Tarbela, Tarbela Dam Project

             Contact #: 0938-281175