Current Status / Progress

1.    Preparatory Works

i.    Relocation of Karakorum Highway (Dasu-KKH-01) 25 km from Dasu town to Kaigah
Contract Agreement between WAPDA and M/s China Civil Engineering Construction Corporation (CCECC) signed on March 16, 2015. The Contractor has commenced services from August 24, 2015 and mobilized to Dasu site. Contractor has established their Site Camps & residences.02 Nos Access Roads to proposed KKH completed. Construction of Asphalt Mixing Plant and Explosive Magazine completed. Installation of Aggregate and Concrete Mixing Plants completed. Excavation work for proposed KKH at various sections is in progress.

ii.    Right Bank Access Road (Dasu-RAR-01) 12 km from Komila to Dam site
Contract Agreement between WAPDA and M/s China Civil Engineering Construction Corporation (CCECC) signed on March 16, 2015. The Contractor has commenced services from August 24, 2015 and mobilized to Dasu site. Contractor has established their Site Camps & residences.Geo-technical investigations at Siglo & Girti bridges sites completed. Widening of existing road at various sections is in progress. 

iii.    132 KV Transmission Line from Dubair HPP to Dasu (Dasu-TL-01) (45 km)
Contract Agreement between WAPDA and M/s Power China signed on April 24, 2015. The Contractor has commenced services from Nov 02, 2015. Contractor has established their Site Camps & residences. Topographic survey, subsoil Investigation, detailed design of route & grid station completed. Excavation of foundation for Towers and concreting is in progress.

iv.    Project Colony and Infrastructure (Dasu-PCI-01R)
Contract Agreement signed between WAPDA and M/s CRFG (China Railway First Group) on November 17, 2015. Mobilization Advance paid to Contractor.Contractor mobilization was delayed due to non-possession of land. Contractor has commenced their services from May 02, 2016. Contractor has established their temporary camp at site.

v.    Relocation of Karakorum Highway (Dasu-KKH-02) 37 km from Kaigah to Sazin
Bids opened on October 27, 2015. 03 Nos. bidders submitted bids. Evaluation of bids completed and submitted to World Bank and CCC for NOL & vetting respectively in December 2015. World Bank has issued NOL to Bid Evaluation Report (BER) on March 08, 2016. WAPDA Authority approved the BER on June 13, 2016 to award the Contract to the lowest responsive bidder.

vi.    Right Bank Access Road (Dasu-RAR-02) 42 km from Dam site to Uttar Gah
Bids opened on October 27, 2015. 03 Nos. bidders submitted bids. Evaluation of bids completed and submitted to World Bank and CCC for NOL & vetting in December 2015. World Bank issued NOL to Bid Evaluation Report (BER) on February 10, 2016. WAPDA Authority approved the BER on June 13, 2016 to award the Contract to the lowest responsive bidder.Contract Discussion meeting with lowest bidder was held on June 16, 2016 to finalize the Contract Agreement. Contractor has also submitted performance guarantee which is under vetting. Contract shall be signed soon.

vii.    Right Bank Access Road (Dasu-RAR-03) 27 km from Uttar Gah to Tangir
Detailed design has been completed. Pre-qualification Documents are under preparation.

viii.    Project Colony and Infrastructure (Dasu-PCI-02R)
Detailed design has been completed. Pre-qualification Documents are under preparation.

 

2.    Main Works

              i.       RCC Dam & Appurtenant Structures (Dasu-MW-01)

       ii.       Underground Powerhouse & Appurtenant Structures (Dasu-MW-02).

Current Status

  • Bids for Main Civil Works Contracts (Dasu-MW-01 & Dasu-MW-02) received & opened by deadline July 11, 2016 (1130 hrs) in WAPDA Auditorium, Wapda House, Lahore. Member (Water) chaired by Bid Opening Ceremony attended by all members of Bid Opening Committee and representatives of Contractors.
  • It may be noted that 7 Nos. Contractors pre-qualified for MW-01 and 6 Nos. for MW-02. Out of which, 4 Nos. Contractors participated in bidding process for MW-01 and 3 Nos. for MW-02.
  • Consultants prepared the Bid Evaluation Report (BER) for both Contracts and same was sent to World Bank and CCC WAPDA for review.
  • World Bank issued NOL to both BERs on October 05, 2016. Subsequently, WAPDA Authority on October 18, 2016 approved both BERs and to award the Contracts to the lowest response bidders. 

3.    E&M Works

  • The Pre-Qualification applications from interested firms received on August 26, 2016 upto 1100 hours and opened on same day at 1130 hrs in the Committee Room of Dasu Hydropower Project Office, Lahore. Seven (07) No Firms/JVs submitted their PQ Documents for the pre-qualification.
  • Evaluation of PQ Applications in progress by Consultants.

4.    Hydraulic Model Studies
Hydraulic model studies were carried out for Dasu Hydropower Project in order to assess/confirm the design of the project. These studies included construction of a scale model of the project components and their performance through operation with properly scaled discharge. The facilities for these tests are available at Hydraulic Research Station, Nandipur, where the studies were conducted by the WAPDA Model Studies Cell, Irrigation Research Institute, Lahore.
The following models have been prepared and tested:


I.    Comprehensive Model at a Scale of 1:80
i.    Main dam including the spillway with 8 bays and 9 No. low level outlets.
ii.    Flushing tunnels
iii.   River channel reach of about 7Km


II.    Sectional Model of Spillway at a Scale of 1:50 & 1:20
This model of the spillway was comprised of three bays, constructed in transparent Plexiglas, to observe the flow conditions and make elaborate measurements of hydraulic parameters.


III.    Sectional Model of Low Level Outlet at a Scale of 1:40
In this model, a single low level outlet was constructed with transparent material, where the behavior of flow at different discharges was observed and necessary hydraulic measurements recorded.
Comprehensive technical reports prepared by the WAPDA model studies cell, which include all the observed data, photographs of different tests, and recommendations/ conclusions regarding the hydraulic adequacy of the project components.

Current Status
•    International Panel of Experts (IPoEs) visited Nandipur Research Institute and observed demonstration of models.
•    In the light of comments received from IPoEs, few modifications are being done in sectional models.

 