Bhimber Dam Project

Location
Bhimber Dam site is located about 10 km Up Stream Bhimber-Gujrat Road Bridge on Bhimber Nullah in District Bhimber, Azad Kashmir
Salient Features
Dam Type Earth & Rockfill
Height of Dam 192 ft
Gross Storage Capacity 40,000 AF
Live Storage Capacity 28,700 AF
CCA 24,710 Acres
Power Generation 2 MW
Execution by Feasibility Study will be carried out by WAPDA
Donor Agency From WAPDA own resources
Commencement Date July, 2016 (Expected)
Completion Date Study Period: 9 months
Financial Status Local (Rs. Million) FEC (Rs. Million) Total  (Rs. Million)
Original PC-I Cost

86.089

- 86.089

Status

WAPDA requested Govt. of AJ&K on October 28, 2015, being sole beneficiary of the project,to arrange funds amounting to Rs 86.089 Million

Incharge Of The Project      General Manager (Hydro) Planning