Kurram Tangi Dam Project
(a) Total expenditure approved in PC-I amounting to Rs. 17205.267 Million and
revised expenditure due to raising of Dam Height will be Rs. 19445.460 Million.
Basic Objects
- Purposeful and effective use of water resources of Kurram and Kaitu Rivers.
- Irrigate New Areas in Sheratalla Spaira Ragha and Thal Plain in North
Waziristan Agency.
- Improvement in cropping intensity of Command Areas of Civil Canals and Marwat
Canal.
- Installation of Hydro Power Plants to Generate cheap and pollution free
Electricity 83.4 MW.
- Improvement in the socio economic Condition of the most Backward Areas of NWFP
and FATA.
(b) 83.4 MW
Cheep and pollution free electricity.
(c) Total No. of affectees are 12899 (Revised) and paid Rs. 8.038 Million to the
affectees at FR Bannu District.
(d) The land acquisition activities at FR Bannu. District Bannu, District Karak
and North Waziristan Agency is in process. The actual date of completion
according to approved PC-I is 48 Months.
(e) Due to tense situation in tribal area and stoppage the survey work by the
then Chief Minister NWFP, the construction work of Kurram Tangi Dam Project is
not started.
Supplementary Material:
- Kurram Tangi Dam is a multipurpose project. It is located on Kurram river
in North Waziristan Agency about 14 Km upstream of Kurram Garhi head work
and 32Km in North of Bannu city. The height of Dam is 322 ft (Revised) ws
storage capacity of 1.2 MAF. The Command Area of this project is 3,62,380 acres
(Revised). The Project will be generated 83.4 MW electricity and 332 Gwh
energy annually through five houses.
- Presently the demarcation of pond area/dam area at North Waziristan Agency,
District Bannu, District Karak and FR Bannu is completed.
|
ACHIEVEMENT |
|
1.
FR Bannu |
1304.61 Kanal i.e 163.07 acres land have been acquired for
main Thal canal and payment of Rs. 8.038 Million has been made to the
Effectees through DCO Bannu. Some portion has been remained due to
demarcation of FR Bannu and District Bannu boundary. The case of 5.12 Acrs
is in process. |
|
2.
Bannu |
-
Presently the work is in process.
-
Section -IV has been completed for main Thal Canal.
-
Section-V for main Thal Canal/Distributaries is in process.
|
|
3.
Karak |
|
|
4. North Waziristan Agency |
|
|
-
The dam area/pond area is located in North Waziristan
Agency.
-
The demarcation of pond area/Dam Area is completed with paint.
-
Sixty No. Badragas have been approved by the Authority but relaxation for
recruitment of employees has not been accorded from the ban. It is therefore
requested to exempt the Kurram Tangi Dam Project from Ministry of Water and
Power w.e.f 12-04-2008 please.
-
Jirgas are in process
with the elders of Tribal area. They demanded the advance payment of land.
Project Director explained the position to allow the LAC staff to take
measurement and the staff will classify the land i.e. Agriculture/Hilly
area, owner of the land, so that the LAC will prepare estimate and and it
will be submitted to head office for releasing the fund. However this
office is waiting for the decision of political Administration Authority.
|
|
ISSUES
The progress of Kurram Tangi Dam Project is delayed due to the following
reasons. |
|
|
a. Due to tense situation in Tribal area i.e. North
Waziristan Agency.
b. Due to stoppage of Survey work/Land Acquisition by the then Chief
Minister NWFP Peshawar.
c. Due to imposing ban on recruitment of employees by Federal Minister of
Water and Power Development Authority Islamabad w.e.f 12-04-2008. It is
therefore requested to exempt Kurram Tangi Dam Project being located in
Tense area from the ban w.e.f 12-04-2008 please.
|
|
Target 2008-09
The construction work not yet started due to tense situation in Tribal area.
It is hoped to be targeted that the land Acquisition activities will be
started in the tribal area during financial year 2008-09. |
|